MidContinent Express Pipeline LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/10/2009, Docket: RP09-136-000, Status: Effective
Original Sheet No. 107 Original Sheet No. 107
GENERAL TERMS AND CONDITIONS
----------------------------
(a) Shippers are subject to different Gas quality
standards for Gas receipts on the Leased Capacity (See Section 19 of
these General Terms and Conditions).
(b) Shippers have different secondary point rights on
Leased Capacity (See Section 2.4 of these General Terms and
Conditions).
(c) Shippers have different rights to change points on
the Leased Capacity (see Section 2.1(d) of these General Terms and
Conditions).
(d) Shippers cannot segment Leased Capacity (see
Section 6.13 of these General Terms and Conditions).
(e) Shippers pay separate Leased Capacity Charges
which are designed to achieve a flow-through by MEP of charges paid
Enogex. The Leased Capacity Charges include: Reservation Charges
for firm service, a rate per Dth for interruptible service, a rate
for fuel which includes unaccounted for gas, and Leased Capacity
Activity Charges (as defined below). Shippers do not pay MEP's
Reservation Charges, Commodity Charges, Fuel Gas Charges, Unaccounted
For Gas Charges, Balancing Service Charges or other charges with
respect to Leased Capacity. Notwithstanding the foregoing, a
Negotiated Rate or Negotiated Rate Formula may apply to the Leased
Capacity.
(f) A Releasing Shipper cannot segment Leased Capacity
and the price for the release of Leased Capacity is capped at the
level of the Leased Capacity Charges (See Section 14 of these General
Terms and Conditions).
(g) Rights of first refusal shall apply to Leased
Capacity to the extent provided in Section 16.2(a) of these General
Terms and Conditions).