MidContinent Express Pipeline LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/10/2009, Docket: RP09-136-000, Status: Effective
Original Sheet No. 33 Original Sheet No. 33
RATE SCHEDULE ITS
-----------------
3. VALID REQUESTS
3.1 A request for service under this Rate Schedule ITS shall
be valid as of the date received if it complies with this Section and
contains adequate information on all of the items specified in
Section 3.2, subject to any necessary verification of such
information and to the following:
(a) A request shall not be valid and MEP shall not be
required to grant any such request: (1) which would require the
construction, modification, expansion, or acquisition of any
facilities; provided, however, that MEP may agree on a basis not
unduly discriminatory to construct, modify, expand, or acquire
facilities to enable it to perform such services; (2) unless and
until Shipper has provided MEP with the information required in
Section 3.2 hereof; (3) if MEP determines, based on the credit
analysis referenced in Section 3.2(d), that Shipper does not possess
sufficient financial stability to make it reasonably likely the
service provided hereunder will be paid for on a timely basis; (4) if
the service requested would not comply with this Rate Schedule ITS;
or (5) if the service requested is at less than the applicable
maximum rate; provided, however, that MEP may agree to provide
service hereunder at a discount or at a Negotiated Rate or under a
Negotiated Rate Formula, consistent with this Rate Schedule ITS and
the applicable General Terms and Conditions of this Tariff. Nothing
herein is intended to govern the scheduling or curtailment of service
once a request for service has been granted pursuant to this Section
and while an ITS Agreement is in effect. Such scheduling and/or
curtailment are governed by the General Terms and Conditions of this
Tariff.
(b) Any request must be complete and comply with this
Rate Schedule ITS. MEP shall promptly notify Shipper if it cannot
satisfy an otherwise valid request, in whole or in part, due to any
of the reasons set out in Section 3.1(a) or if the request is
incomplete or does not comply with this Rate Schedule ITS. If a
request is not complete, MEP shall inform Shipper in writing of the
specific items needed to complete the ITS Agreement, after which
Shipper shall have fifteen (15) days to provide the specified
information. In the event such information is not received by MEP
within fifteen (15) days, Shipper's request shall be null and void.