MidContinent Express Pipeline LLC

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 04/10/2009, Docket: RP09-136-000, Status: Effective

Original Sheet No. 21 Original Sheet No. 21

 

RATE SCHEDULE FTS

-----------------

 

Delivery Points specified in or applicable to the FTS Agreement. MEP

shall not be required to accept Gas tendered in excess of the Maximum

Daily Quantity (MDQ), plus applicable Fuel Gas and Unaccounted For

Gas, specified in the FTS Agreement for each Receipt Point or

Delivery Point or for the aggregate of all primary Receipt Points or

Delivery Points except as provided in Section 8 of this Rate Schedule

FTS. Service hereunder shall not encompass gathering services,

transportation through the facilities of any third party (except for

facilities leased by MEP which are part of MEP's system), processing,

transportation of liquids, or transportation to processing facilities

unless the FTS Agreement so specifies.

 

2.4 Shipper shall only tender Gas for transportation under

this Rate Schedule to the extent such service would qualify under the

applicable statutes, regulations and Commission orders. For

transportation to be provided under Subpart B of Part 284 of the

Commission's Regulations, Shipper shall provide to MEP certification

including sufficient information in order for MEP to verify that the

service qualifies under Subpart B of Part 284 of the Regulations.

Where required by the Commission's Regulations, Shipper shall cause

the intrastate pipeline or local distribution company on whose behalf

the service will be provided to submit the necessary certification

prior to tendering Gas for transportation.

 

2.5 Awarding and allocation of capacity and scheduling and

curtailment are all governed by the General Terms and Conditions of

this Tariff.

 

2.6 Shipper may release capacity dedicated to service under

Shipper's FTS Agreement(s) hereunder pursuant to MEP's Capacity

Release Program to the extent permitted by, and subject to the terms

and conditions contained in, the General Terms and Conditions of this

Tariff.

 

2.7 MEP may negotiate with Foundation Shipper contractual

provisions under which: (a) a Foundation Shipper has a right to

cause MEP to construct Preapproved Capacity and also has the right to

acquire such Preapproved Capacity at a mutually agreed rate and term,

upon timely exercise by the Foundation Shipper of such capacity

acquisition rights; and/or (b) a Foundation Shipper has the right,

within a period of up to five (5) years after the Commencement Date,

to acquire unsubscribed firm System capacity other than Preapproved

Capacity at an agreed rate for an agreed term.