Original Sheet No. 21 Original Sheet No. 21
RATE SCHEDULE FTS
-----------------
Delivery Points specified in or applicable to the FTS Agreement. MEP
shall not be required to accept Gas tendered in excess of the Maximum
Daily Quantity (MDQ), plus applicable Fuel Gas and Unaccounted For
Gas, specified in the FTS Agreement for each Receipt Point or
Delivery Point or for the aggregate of all primary Receipt Points or
Delivery Points except as provided in Section 8 of this Rate Schedule
FTS. Service hereunder shall not encompass gathering services,
transportation through the facilities of any third party (except for
facilities leased by MEP which are part of MEP's system), processing,
transportation of liquids, or transportation to processing facilities
unless the FTS Agreement so specifies.
2.4 Shipper shall only tender Gas for transportation under
this Rate Schedule to the extent such service would qualify under the
applicable statutes, regulations and Commission orders. For
transportation to be provided under Subpart B of Part 284 of the
Commission's Regulations, Shipper shall provide to MEP certification
including sufficient information in order for MEP to verify that the
service qualifies under Subpart B of Part 284 of the Regulations.
Where required by the Commission's Regulations, Shipper shall cause
the intrastate pipeline or local distribution company on whose behalf
the service will be provided to submit the necessary certification
prior to tendering Gas for transportation.
2.5 Awarding and allocation of capacity and scheduling and
curtailment are all governed by the General Terms and Conditions of
this Tariff.
2.6 Shipper may release capacity dedicated to service under
Shipper's FTS Agreement(s) hereunder pursuant to MEP's Capacity
Release Program to the extent permitted by, and subject to the terms
and conditions contained in, the General Terms and Conditions of this
Tariff.
2.7 MEP may negotiate with Foundation Shipper contractual
provisions under which: (a) a Foundation Shipper has a right to
cause MEP to construct Preapproved Capacity and also has the right to
acquire such Preapproved Capacity at a mutually agreed rate and term,
upon timely exercise by the Foundation Shipper of such capacity
acquisition rights; and/or (b) a Foundation Shipper has the right,
within a period of up to five (5) years after the Commencement Date,
to acquire unsubscribed firm System capacity other than Preapproved
Capacity at an agreed rate for an agreed term.