MidContinent Express Pipeline LLC

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 03/01/2009, Docket: RP09-369-000, Status: Effective

Original Sheet No. 14P Original Sheet No. 14P

 

STATEMENT OF NEGOTIATED RATE TRANSACTIONS

PURSUANT TO SECTION 30

------------------------------------------

 

 

 

Rate Term of Volume Reservation Commodity Primary Receipt Primary Delivery

Shipper Name Schedule Contract Dth/d) Charge(s) Charge(s) Point(s) / PIN No(s). Point(s) / PIN No(s).

-------------------------------- --------- ----------- ---------- ------------ ------------ ------------------------ -------------------

 

SandRidge Energy FTS 1/ 3/ 2/ 2/ 2/ 2/

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

-------------------------------

 

1/ Term of the Agreement begins on the later of (i) February 28, 2009 or (ii) the first day of the calendar month following notice from MEP that the pipeline is

ready to provide firm service from Bennington, OK (PIN No. 44438) to the point of interconnection with Transcontinental Gas Pipe Line in Choctaw County, AL at

Transco's Station 85 (PIN No. 44451) and continues for ten (10) years thereafter.

 

2/ This information is set out in the executed Transportation Rate Schedule FTS Agreement and corresponding Negotiated Rate Exhibit, which are currently on file

with the FERC.

 

3/ Volumes is 75,000 Dth/d for Years 1 through 5 and 50,000 Dth thereafter.