20. FORCE MAJEURE
If either party is rendered wholly or partially unable to carry out its
obligations due to force majeure, the affected party must give notice to the
other party as soon as is reasonably possible after the occurrence and provide
the full particulars of the force majeure either in writing, by facsimile or
via electronic means. So far as they are affected by the force majeure, the
obligations of the parties, other than to make payments of amounts due
(including any applicable reservation charge), shall be suspended during the
continuance of any inability so caused, but no longer. If either party fails
to rectify the force majeure within 90 days, either party may, at its
reasonable discretion, terminate the transportation service agreement. If
Shipper is unable to carry out its obligation due to force majeure, White
River may seek to make any of Shipper's capacity available to other Shippers
or to offer any available service to others. Shipper may again apply for
service under this FERC Gas Tariff at such time as Shipper's force majeure
condition is corrected.