White River Hub, LLC

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/01/2008, Docket: RP08-645-000, Status: Effective

Original Sheet No. 104 Original Sheet No. 104

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

10. USE OF RECEIPT AND DELIVERY POINTS

 

10.1 Designation of primary receipt and delivery points. Shipper's

primary receipt and delivery points must be assigned by the Shipper, subject

to available capacity. The sum of the RDC assigned to Shipper's Primary

Receipt points must equal the sum of the RDC assigned to the Primary Delivery

points. The sum of the Primary Receipt point RDC and the sum of the Primary

Delivery point RDC must equal the RDC shown in Shipper's Rate Schedule FT or

RGS service agreement.

 

10.2 Adding and deleting points or changing capacity at primary receipt

and delivery points. A firm Shipper may request to add and delete primary

receipt and delivery points and increase or decrease its RDC at primary

receipt and delivery points subject to available capacity by amending its

transportation service agreement. A firm Shipper that requests primary firm

capacity at a new receipt or delivery point must either (1) release equivalent

capacity at one or more existing receipt or delivery points or (2) request and

pay for additional primary capacity.

 

Rate Schedule RGS Shippers may only add qualifying Primary Receipt

points as described in Rate Schedule RGS.

 

Amendment requests shall be posted no later than 9:00 a.m. the day

nominations are due. White River will evaluate amendment requests in a timely

manner except as limited by § 5.11.

 

Approved requests to change primary receipt or delivery points or

Shipper's RDC will be posted on the Customer Activities Web site by 10:00 a.m.

on the third business day following the amendment request date except for

limitations explained in § 5.11 which will be posted the third business day

following the bid period.

 

White River will not allow amendments to contracts to change Primary

Receipt and Primary Delivery points if the result of the requested amendment

impairs White River's ability to provide firm service. Any capacity at

receipt and delivery points that becomes available through the expiration of

a firm transportation agreement will be sold according to the bidding

procedures outlined in §§ 5 and 7, and shall not be available for primary

receipt or delivery-point changes unless White River, without undue

discrimination, agrees otherwise.