White River Hub, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/2008, Docket: RP08-645-000, Status: Effective
Original Sheet No. 14 Original Sheet No. 14
RATE SCHEDULE FT
FIRM TRANSPORTATION SERVICE
(Continued)
White River shall file with the Commission any and all reports as
required by the Commission's Regulations setting forth the applicable charges,
the individual Shippers affected, the quantity of gas transported and any
other information that may be required.
3.4 Negotiated Rates. Notwithstanding anything to the contrary
contained in this tariff, White River and Shipper may, as provided in § 27
(Negotiated Rates) of the General Terms and Conditions, negotiate a rate for
service under this rate schedule. White River's rates, as shown on its
Statement of Rates, are available as recourse rates for any Shipper that does
not desire to negotiate a rate with White River. An agreement by the Shipper
to accept a negotiated rate does not, in any manner, restrict the Shipper's
right to elect recourse rates for other services not covered by the
negotiated-rate agreement. This provision, in and of itself, does not allow
White River and Shipper to negotiate terms and conditions of service.
4. REGULATORY FEES
Shipper shall reimburse White River for all fees required by the
FERC or any other regulatory agency to implement the service provided under
this rate schedule. No reimbursement will be required for regulatory fees
generally applicable to all shippers, e.g., an NGA § 4(e) rate filing, § 7(c)
certificate application, or for any fee that does not specifically relate to
Shipper's transportation service under Rate Schedule FT.
White River will issue a statement to Shipper setting forth the fees
paid by White River to implement the transportation service. The amount to
be reimbursed shall be paid by Shipper with the next payment for service
following receipt of White River's statement.