Arlington Storage Company, LLC
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/08/2009, Docket: RP10-67-000, Status: Effective
Original Sheet No. 154 Original Sheet No. 154
GENERAL TERMS AND CONDITIONS
(Continued)
27.3 In the event ASC shall have suspended service pursuant to Section 27.2, Customer may cause
ASC to resume or continue service by providing an advance payment equal to one Month's
charges for service under the Customer's Storage Service Agreement(s) and providing
Financial Assurances pursuant to Section 30 of these General Terms and Conditions within
thirty (30) days of ASC's notice of suspension. Customer shall not be obligated to pay ASC
reservation charges for any suspended services during any period of suspension pursuant
to Section 27.2.
28. POLICY WITH RESPECT TO FEES AND CONSTRUCTION OF NEW FACILITIES
28.1 Except as provided in Section 28.2 herein, Customer shall reimburse ASC (a) for the costs
of any facilities installed by ASC with Customer's consent to receive, measure, store or
deliver Gas for Customer's account and (b) for any and all filings and approval fees required
in connection with Customer's Storage Service Agreement that ASC is obligated to pay to the
Commission or any other governmental authority having jurisdiction. Any reimbursement
due ASC by Customer pursuant to this Section 28.1 shall be due and payable to ASC within
ten (10) days of receipt by Customer of ASC's invoice(s) for same; provided, however, that
subject to ASC's consent, such reimbursement, plus carrying charges thereon, may be amortized
over a mutually agreeable period not to extend beyond the primary contract term of the Storage
Service Agreement between ASC and Customer. Carrying charges shall be computed utilizing
interest factors acceptable to both ASC and Customer.
28.2 ASC may waive from time to time, at its discretion, all or a portion of the facility cost
reimbursement requirement set forth in Section 28.1 for Rate Schedules FSS, NNSS, FP and FL
if Customer provides ASC adequate assurances to make construction of the facilities economical
to ASC. All requests for waiver shall be handled by ASC in a manner which is not unduly
discriminatory. For purposes of determining whether a project is economical, ASC will
evaluate projects on the basis of various economic criteria, which will include the estimated
cost of the facilities, operating and maintenance as well as administrative and general
expenses attributable to the facilities, the revenues ASC estimates will be generated as a
result of such construction, and the availability of capital funds on terms and conditions
acceptable to ASC. In estimating the revenues to be generated, ASC will evaluate the existence
of capacity limitations downstream of the facilities, the marketability of the capacity, the
Interruptible versus the firm nature of the service, and other similar factors which impact
whether the available capacity will actually be utilized.
29. OFF-SYSTEM CAPACITY
ASC may, from time to time, acquire transportation and/or storage capacity on
a third-party pipeline system. ASC will only provide transportation and storage
services for others using such capacity pursuant to its open access FERC Gas
Tariff subject to its rates approved by the Federal Energy Regulatory Commission,
and the "shipper must hold title" policy is waived to permit such use.