Arlington Storage Company, LLC
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/08/2009, Docket: RP10-67-000, Status: Effective
Original Sheet No. 28 Original Sheet No. 28
FP RATE SCHEDULE
FIRM PARKING SERVICE
1. AVAILABILITY
This Rate Schedule is available to any Customer for the purchase of firm parking service
from ASC, provided that:
(a) ASC has determined that it has sufficient operationally available firm storage
capacity, injection and withdrawal capacity to perform the firm parking service
Customer has requested;
(b) Customer and ASC have executed a Firm Parking Service Agreement under this
Rate Schedule;
(c) Customer accepts responsibility for arranging any transportation service required
for utilization of the firm parking service provided under this Rate Schedule;
(d) Availability of service under this Rate Schedule shall be subject to a determination
by ASC that its performance of the service requested hereunder shall not cause a
reduction in ASC's ability to provide Firm Storage Services under currently effective
Storage Service Agreements; and
(e) Service under this Rate Schedule may not be available to the extent that ASC would
be required to construct, modify, expand or acquire any facilities to enable ASC
to perform the requested services.
2. APPLICABILITY AND CHARACTER OF SERVICE
This Rate Schedule shall apply to all firm parking service rendered by ASC to Customer through use
of ASC's storage facility located in Steuben County, New York pursuant to an executed Firm Parking
Service Agreement. Firm parking service rendered by ASC to Customer under this Rate Schedule shall
consist of:
(a) The receipt on any Day during the Injection Period stated in Customer's executed
Firm Parking Service Agreement and injection into storage of Customer's Gas per
Customer's nomination up to the Maximum Daily Injection Quantity ("MDIQ")
stated in Customer's executed Firm Parking Service Agreement, provided that
Customer delivers the nominated quantity plus Fuel Reimbursement to the Point(s)
of Receipt, and Customer's Park Balance has not exceeded Customer's Maximum Park
Quantity;
(b) The tender by Customer of sufficient quantities of Gas under Section 2(a) to ensure
that Customer's Park Balance equals Customer's Maximum Park Quantity at the end of
the Injection Period, provided that, if Customer's injections during the Injection
Period are curtailed by ASC, Customer shall have a reasonable period of time
immediately following the Injection Period to make injections as necessary for
Customer's Park Balance to equal its Maximum Park Quantity;
(c) The storage of Gas in amounts up to Customer's Maximum Park Quantity; and