Arlington Storage Company, LLC

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 08/24/2009, Docket: RP09-872-000, Status: Effective

Original Sheet No. 29 Original Sheet No. 29

 

FP RATE SCHEDULE

FIRM PARKING SERVICE

(Continued)

 

(c) The storage of Gas in amounts up to Customer's Maximum Park Quantity; and

 

 

(d) The withdrawal from storage on any Day during the Withdrawal Period stated in

Customer's executed Firm Parking Service Agreement and delivery of Customer's Gas

per Customer's nomination to the Point(s) of Delivery up to the Maximum Daily

Withdrawal Quantity ("MDWQ") as stated in Customer's executed Firm Parking Service

Agreement, provided that Customer has a quantity of Gas in Customer's Park Balance

not less than the quantity Customer shall have nominated for withdrawal on such Day.

 

Customer shall not have the right to inject or withdraw Gas during the period of time between

the Injection Period and the Withdrawal Period.

 

2.2 Provided the receipt of Gas from Customer and the injection of such Gas into

storage can be accomplished by ASC without detriment to ASC's facilities and

ASC's ability to meet its firm obligations to other Customers, ASC may, upon

request of Customer and after confirmation by Customer's Transporter, schedule

and inject on an Interruptible basis quantities of Gas in excess of Customer's

MDIQ, provided that Customer's firm Storage Inventory has not exceeded Customer's

Maximum Storage Quantity. Such excess quantities shall be deemed to be

"Excess Injection Gas."

 

2.3 Provided such withdrawal of Gas from storage and delivery of such Gas to Customer

can be accomplished by ASC without detriment to ASC's facilities and/or

ASC's ability to meet its firm obligations to other Customers, ASC may, upon

request of Customer and after confirmation by Customer's Transporter, schedule

and withdrawal on an Interruptible basis quantities of Gas in excess of Customer's

MWQ, provided that Customer has sufficient Gas stored in Customer's firm Storage

inventory. Such excess quantities shall be deemed to be "Excess Withdrawal Gas."

 

 

3. RATES AND CHARGES

 

Customer shall pay rates and charges for firm parking service under this Rate Schedule including

the applicable parking rate components set forth in the FP Rate Statement and as described below:

 

(a) Firm Parking Reservation Charge. A monthly charge for each Dth of Customer's

Maximum Park Quantity.

 

(b) Firm Parking Injection Charge. A charge for each Dth of Customer's Gas injected

into ASC's facilities pursuant to Section 2.1(a) of this Rate Schedule during a

given Month.

 

(c) Firm Parking Withdrawal Charge. A charge for each Dth of Customer's Gas withdrawn

from ASC's facilities pursuant to Section 2.1(d) of this Rate Schedule during a

given Month.

 

(d) Fuel Reimbursement. The amount of Gas for fuel and losses determined in accordance

with Section 19 of the General Terms and Conditions of this FERC Gas Tariff and set

forth in Customer's Firm Parking Service Agreement.

 

(e) Regulatory Fees and Charges. Customer shall reimburse ASC for all fees and charges,

as required by the Commission or any other regulatory body, that are related to

service provided under this Rate Schedule, as set forth in Customer's Firm Parking

Service Agreement.

 

(f) Taxes. Customer shall reimburse ASC for all applicable taxes as may be assessed

ASC, as set forth in Section 15 of the General Terms and Conditions of this FERC

Gas Tariff and in Customer's Firm Parking Service Agreement.