National Fuel Gas Supply Corporation
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/01/1997, Docket: RP97-201-000, Status: Effective
Fourth Revised Sheet No. 210 Fourth Revised Sheet No. 210 : Superseded
Superseding: Third Revised Sheet No. 210
GENERAL TERMS AND CONDITIONS
16. CURTAILMENT (cont'd)
16.2 Curtailment of Storage Injection and Withdrawal Capacity (cont'd)
(vii) last, to quantities scheduled within contract quantities
for each Shipper pursuant to the FSS, SS-1, SS-2, ESS, or
other firm storage service rate schedule.
Available capacity will be allocated to scheduled injections and
withdrawals within a category for purposes of this Subsection in
proportion to the quantities scheduled by Transporter.
16.3 Limitation of Storage Capacity
If, on any day, Transporter determines that the available storage
capacity on its system, or any portion thereof, is insufficient to
serve all storage capacity requirements which are otherwise
scheduled to receive service on such day, capacity which requires
allocation shall be allocated in a manner which results in
curtailment of capacity, to zero (0) if necessary, first to
capacity scheduled pursuant to the P-2 Rate Schedule, and then to
capacity scheduled for storage pursuant to the IR-2 Rate Schedule,
and then to capacity scheduled pursuant to the ISS Rate Schedule,
and then to capacity scheduled pursuant to the FSS, SS-1, SS-2,
ESS, or other firm storage service rate schedules. Available
capacity will be allocated to scheduled capacity within each
category for purposes of this Subsection in proportion to the
quantities scheduled by Transporter.