National Fuel Gas Supply Corporation
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/05/1996, Docket: RP96-333-000, Status: Effective
First Revised Sheet No. 82 First Revised Sheet No. 82 : Superseded
Superseding: Original Sheet No. 82
IAS RATE SCHEDULE
INTERRUPTIBLE ADVANCE SERVICE
3. QUALIFICATION FOR SERVICE (Cont'd.)
prepayment or other security provided as set forth above, or
as is necessary to ensure that neither Shipper's net worth,
nor its unencumbered assets in the states in which Seller
operates is less than an amount equal to the highest Nega-
tive Imbalance Cash-Out Price (set forth at Section 14.10(a)
of the General Terms and Conditions) occurring during the
twelve (12) month period preceding the date service is
requested times the quantity of advanced gas requested.
3.3 (a) Upon Transporter's determination that Shipper's request for
service is complete, Transporter will enter such request on
a list of pending complete requests and so notify shipper.
Transporter will evaluate its ability to satisfy complete
requests for service received in their order of entry on
such list. Transporter shall process requests for service
within a reasonable period of time. If Transporter rejects
a request for service which has been entered on Trans-
porter's list of pending complete requests, Transporter will
so notify Shipper within ten (10) days of such rejection.
In such event, Shipper's request for service will not remain
entered on such list unless Shipper notifies Transporter,
within thirty (30) days of Transporter's notification of
rejection, that its request should remain so entered. Upon
receipt of such written notification by Shipper, Shipper's
request will remain entered for an additional six (6)
months, and for additional three (3) month periods thereaf-
ter, provided that Shipper notifies Transporter, in writing,
prior to the conclusion of a three (3) month period, that it
requests an extension.
(b) An IAS Service Agreement shall be executed by Shipper and
Transporter following Transporter's acceptance in writing of
Shipper's request for service. In the event the IAS Service
Agreement is not executed and returned by Shipper within
thirty days after Transporter tendered the agreement, Trans-
porter shall consider the request for service invalid.