National Fuel Gas Supply Corporation
Fourth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/1997, Docket: RP97- 1-011, Status: Effective
Sub. Original Sheet No. 865 Sub. Original Sheet No. 865 : Effective
INTERCONNECTION AGREEMENT
ARTICLE I
(Cont'd)
(B) Operator shall deliver gas at a pressure sufficient to enable
such gas to enter Transporterþs facilities against the pressure prevailing
therein from time to time, provided, however, that Operator shall not deliver
gas at any Receipt Point at a pressure in excess of the pressure designated
by Transporter.
(C) Operator warrants that all compression operations shall be
conducted in a manner (i) so as to prevent the pulsations therefrom from
interfering with Transporterþs measurement at any Receipt Point, and (ii) so
that compressed gas will be delivered to Transporter at a temperature not
exceeding one hundred twenty degrees Fahrenheit (120ø F).
(D) Operator shall give Transporter written notice at least twenty-
four (24) hours prior to the commencement of (or any material change in)
compression operations that may affect delivery conditions at a Receipt
Point.
(E) Operator shall give Transporter written notice at least twenty-
four (24) hours prior to any material change in the maintenance routine
applicable to any compressor used in its operations.