National Fuel Gas Supply Corporation
Fourth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/21/2010, Docket: RP10-504-000, Status: Effective
Second Revised Sheet No. 56 Second Revised Sheet No. 56
Superseding: First Revised Sheet No. 56
EFT RATE SCHEDULE
Enhanced Firm Transportation Service
4. OPERATING PROTOCOL FOR EFT SERVICE (Cont'd.)
Pressure
Interconnecting Requirement Capacity
Pipeline Meter Name/Location Meter PSIG DT/Day
Texas Eastern Transmission Bristoria 0015 750 103000
Texas Eastern Transmission Bristoria 5054 750 103000
Three Rivers Pipeline Three Rivers P.L TRP268 450 10000
TransCanada Pipelines Ltd. Niagara 1-0902 725 236500
Transcontinental Gas Pipe Line Leidy 4494 1100 400000
Transcontinental Gas Pipe Line Leidy 3549 1100 400000
Transcontinental Gas Pipe Line Wharton 6172 600 139050
Transcontinental Gas Pipe Line Wharton 3261 600 139050
4.4 Storage Requirements
This section sets forth the range of injection and withdrawal
capabilities associated with each individual storage field
operated by Transporter. Transporter's ability to transport
quantities of gas between Transporter's storages under the EFT
Rate Schedule and particular receipt and delivery points may be
constrained by these field specific capabilities.
In addition, during the injection cycle specific storages can only
be filled from a single interconnection to an upstream pipeline.
In New York; Nashville, Perrysburg, Sheridan and Colden storages
can only be filled from the facilities of Tennessee Gas Pipeline
Company. Similarly, in Pennsylvania; Hebron Storage can only be
filled from Tennessee Gas Pipeline Company.
Therefore, EFT Shippers who have upstream capacity on Tennessee
Gas Pipeline Company will have to arrange for quantities to be
scheduled on Tennessee Gas Pipeline Company for injection into
these specific storages.