FT RATE SCHEDULE
Firm Transportation Service
1. AVAILABILITY
1.1 This rate schedule is available for transportation service by
National Fuel Gas Supply Corporation (hereinafter called
"Transporter") for any person (hereinafter called "Shipper")
provided that: (i) capacity is available on all portions of
Transporter's system (including primary receipt and delivery
points) necessary to provide service on a firm basis throughout
the requested term; (ii) Shipper makes a request for service as
set forth in Section 31 of the General Terms and Conditions and
executes a service agreement for firm transportation service
under this FT Rate Schedule in the form contained in this Tariff;
and (iii) said service complies with the terms and conditions of
this FT Rate Schedule.
1.2 For purposes of determining the availability of service in
processing requests for service hereunder, Transporter shall not
grant any said request for transportation service: (i) for which
capacity is not available on any portion of its system necessary
to provide such service on a firm basis; provided, however, that
Transporter may not reject a request for service hereunder solely
because of the absence of equipment sufficient to provide
Transporter with real time measurement, communication and control
capability at any delivery point, unless the installation of such
equipment would not be operationally feasible, as determined by
Transporter; (ii) which could in Transporter's judgment interfere
with the integrity of its system, or service to existing firm
transportation or storage customers; or (iii) if such service
does not comply with this FT Rate Schedule or the FT Service
Agreement. Transporter shall not be required to grant any said
request for transportation service which would require the
construction, modification, expansion or acquisition of any
facilities. Availability of service is also subject to Section
31 of the General Terms and Conditions - Qualification for
Service.
1.3 While a determination of capacity on Transporter's system is
reported once each year, on March 1st, in accordance with Section
284.13(d)(2) of the Commission's regulations, determination of
available firm capacity on Transporter's system shall be made