Maritimes & Northeast Pipeline, L.L.C.

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 01/01/2009, Docket: RP09-73-001, Status: Effective

Sub Fourth Revised Sheet No. 249A Sub Fourth Revised Sheet No. 249A

Superseding: Fourth Revised Sheet No. 249A

 

GENERAL TERMS AND CONDITIONS

(continued)

 

9. CAPACITY RELEASE (continued)

 

(16) the recall notification period(s), as identified

in Section 9.6(b)(4) below, that will be

available for use by the parties.

 

(17) the priorities that Pipeline is authorized to

utilize in the event that overlapping nominations

submitted by the Releasing Customer and any

Replacement Customer are in excess of the

Releasing Customer's original MDTQ;

 

(18) whether the Releasing Customer will allow the

Replacement or Prearranged Customer to amend the

Primary Point(s) of Receipt and/or Primary

Point(s) of Delivery after the capacity is

awarded;

 

(19) whether the Prearranged Customer is affiliated

with the Releasing Customer;

 

(20) whether the Releasing Customer will allow the

Replacement or Prearranged Customer to re-release

the capacity acquired from the Releasing

Customer.

 

(21) whether the proposed release is to an asset

manager as part of an asset management

arrangement as defined in Section 284.8(h)(3) of

the Commission's regulations or to a marketer

participating in a state-mandated retail access

program as defined in Section 284.8(h)(4) of the

Commission's regulations, and, if as part of an

asset management arrangement, the volumetric

level of the asset manager's delivery or purchase

obligation and the time period during which the

obligation is in effect.

 

(22) for purposes of bidding and awarding, any maximum

and/or minimum rates specified by Releasing

Customer shall include the tariff reservation

rate and all demand surcharges, specified as a

total number or as stated separately. For

releases that become effective on or after July

30, 2008, the maximum and/or minimum rates

specified by Releasing Customer may exceed the

maximum tariff rate for the applicable service if

(i) the term of the proposed release is one (1)

year or less, and (ii) the effective date of the

proposed release is on or before one (1) year

from the date on which Pipeline is notified of

the release, subject to the restrictions in

Section 9.11 herein.