5. SERVICE NOMINATION PROCEDURE

 

 

(b) The sum of the Quantities nominated at Point(s) of

Receipt less applicable Fuel Retainage Quantities

shall equal the sum of the Quantities of Gas nominated

at Point(s) of Delivery during the Month. In

addition, the Quantity of Gas nominated at each

Primary Point(s) of Receipt shall not exceed the MDRO

plus applicable Fuel Retainage Quantity, and the

Quantity of Gas nominated at each Primary Point of

Delivery shall not exceed the MDDO.

 

5.2 Initial Nominations. The nomination of deliveries under

all rate schedules to commence on the first Day of any

Nomination Period shall be submitted to Pipeline no later

than the time specified in the nomination timeline below,

or such lesser period as is acceptable to Pipeline, prior

to the first Day of the Nomination Period. Such nomination

shall specify the quantity to be scheduled for each Day of

the Nomination Period.