3. SERVICE REQUESTS AND CONTRACTING FOR SERVICE (continued)
(g) Customer/Interconnecting Party shall confirm at the
time of the Request in writing for the benefit of
Pipeline that no significant claims, lawsuits, or
judgments are outstanding which would materially
affect Customer's or (if applicable) its guarantor's
ability to remain solvent as a business entity.
3.8 Upon notification by Pipeline that Customer/Interconnecting
Party has failed to satisfy the credit criteria for a Long
Term Service Agreement, or subsequently during the term of
a Long Term Service Agreement if Customer no longer
satisfies such credit criteria in which case Customer shall
notify Pipeline that Customer or (if applicable) Customer's
guarantor fails to continue to satisfy the credit criteria
set forth in Section 3.7, immediately upon becoming aware
of such failure, such Customer may still obtain credit
approval by Pipeline if it elects to provide one of the
following:
(a) an advance deposit in the amount specified below;
(b) a standby irrevocable letter of credit from a
financial institution acceptable to the Pipeline in
the amount specified below;
(c) security interest in collateral satisfactory to
Pipeline; or
(d) a guaranty, acceptable to Pipeline, by another person
or entity which satisfies the credit appraisal
criteria set forth in Section 3.7.
If Customer/Interconnecting Party provides an advance
deposit or other credit instrument and then
subsequently satisfies or obtains a guaranty from an
entity that satisfies the credit criteria set forth in
Section 3.7, Pipeline shall return to
Customer/Interconnecting Party any such advance
deposit or credit instrument with interest where
applicable at the same rate as prescribed for pipeline
refunds as set forth in Section 154.501(d) of the
Commission's Regulations under the Natural Gas Act.