RATE SCHEDULE MNPAL

PARK AND LOAN SERVICE

(continued)

 

 

8. IMPAIRMENT OF RECEIPTS AND DELIVERIES

 

8.1 If Pipeline, on any Day, is unable to receive and/or deliver the total

requests of all Customers on Pipeline's system, Pipeline shall limit

receipts and/or deliveries of gas hereunder in accordance with

Sections 8 and 26 of Pipeline's GT&C.

 

8.2 For purposes of restricting MNPAL services, Pipeline will give

priority to MNPAL transactions based on net present value, with the

transaction yielding the highest value receiving a higher priority

than other transactions yielding lower values.

 

8.3 Customer may be required, upon notification from Pipeline, to suspend

or reduce receipts or deliveries for the agreed upon Park Service

and/or the agreed upon Loan Service. Further, Customer may be

required, upon notification from Pipeline, to remove quantities of gas

previously provided to Pipeline under the Park service, or return

quantities of gas previously loaned to Customer under the Loan

service. Notwithstanding anything to the contrary in Section 2 of

Pipeline's GT&C, such notification shall be provided to affected

parties through the affected party's choice of Electronic Notice

Delivery mechanism(s).

 

8.4 Should Pipeline notify Customer to remove or return quantities of gas

pursuant to Section 8.3, Pipeline's notification shall specify the

time frame, which shall be no less than twenty-four (24) hours, within

which Park service quantities shall be removed, or Loan service

quantities shall be returned. Such notifications shall be consistent

with Pipeline's operating conditions, unless Pipeline and Customer

mutually agree to a different specific time. The obligation of

Customer to comply with the issued notification shall continue until

such time as Pipeline is able to recommence the MNPAL services. In

the event that Customer does not comply with Pipeline's notice, the

parked balance or the loaned balance will be resolved in accordance

with Sections 8.6 and 8.7, as applicable, of this Rate Schedule MNPAL.

 

To the extent that Customer is unable to comply with Pipeline's notice

either to remove parked quantities or to return loaned quantities because

Pipeline is not able to schedule Customer's nomination for such transactions,

the MNPAL penalties set forth in Sections 8.6 and 8.7, as applicable, shall

not be assessed for those quantities that Pipeline is unable to schedule

during such period in accordance with nominations submitted by Customer in an

effort to comply with the requirements of this Section 8.4.