Maritimes & Northeast Pipeline, L.L.C.

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 01/07/2008, Docket: RP08-113-000, Status: Effective

Second Revised Sheet No. 111 Second Revised Sheet No. 111 : Effective

Superseding: First Revised Sheet No. 111

RATE SCHEDULE MN151

151 DAY FIRM TRANSPORTATION SERVICE

(continued)

 

4. POINTS OF RECEIPT AND DELIVERY (continued)

 

4.4 Notwithstanding anything to the contrary in Sections 4.1

and 4.2 of this Rate Schedule, no point of interconnection

between the facilities of Pipeline and the facilities of

another operator that is located on any portion of

Pipeline's system designated as an Incremental Lateral

(other than point(s) of interconnection between Pipeline's

mainline and any Incremental Lateral) shall be available

under this Rate Schedule as a Primary or Secondary Point of

Receipt or a Primary or Secondary Point of Delivery.

 

5. NOMINATIONS AND SCHEDULING OF RECEIPTS AND DELIVERIES

 

If Customer desires transportation of natural gas on any Day

under this Rate Schedule, Customer must nominate service in

accordance with Sections 5 and 6 of the GT&C.

 

6. IMBALANCES

 

Imbalances are defined in Section 11.1 of the GT&C. Resolution

of imbalances between receipts and deliveries associated with

transportation under this Rate Schedule and Service Agreements

under this Rate Schedule are governed by and resolved pursuant

to Section 11 of the GT&C.

 

7. RESERVATIONS

 

Pipeline reserves the right to take actions as may be required

to preserve the integrity of Pipeline's system, including

maintenance of service to other Customers.