FORM OF SERVICE AGREEMENT
FOR RATE SCHEDULE FTS-5
(Continued)
Customer agrees that Pipeline shall have the unilateral right to file with the appropriate
regulatory authority and make changes effective in (a) the rates and charges applicable to service
pursuant to Pipeline's Rate Schedule FTS-5, (b) Pipeline's Rate Schedule FTS-5 pursuant to which
service hereunder is rendered or (c) any provision of the General Terms and Conditions applicable
to Rate Schedule FTS-5; provided however, Pipeline shall not have the right without the consent
of Customer to make any filings pursuant to Section 4 of the Natural Gas Act to change the MDQ
specified in Article I, to change the term of the service agreement as specified in Article II, to
change Customer Point(s) specified in Article IV, to change the CNG Point(s) specified in Article
IV, or to change the firm character of the service hereunder. Pipeline agrees that Customer may
protest or contest the aforementioned filings, or may seek authorization from duly constituted
regulatory authorities for such adjustment of Pipeline's existing FERC Gas Tariff as may be found
necessary to assure that the provisions in (a), (b), or (c) above are just and reasonable.
ARTICLE IV
CUSTOMER POINT(S) AND CNG POINT(S)
Natural Gas to be received by Pipeline for Customer's account for service hereunder shall be
received on the outlet side of the measuring station at or near the following designated Customer
Point(s) or CNG Point(s), and Natural Gas to be delivered by Pipeline for Customer's account
hereunder shall be delivered at the outlet side of the measuring stations at or near the following
designated CNG Point(s) or Customer Point(s), in accordance with the Maximum Daily Receipt
Obligation (MDRO) plus Applicable Shrinkage, Maximum Daily Delivery Obligation (MDDO), receipt and
delivery pressure obligations and measurement responsibilities indicated below for each:
Customer Maximum Daily Pressure Measurement
Point Obligation Obligation Responsibilities
CNG Maximum Daily Pressure Measurement
Point Obligation Obligation Responsibilities
provided, however, receipt of Gas by Pipeline for Customer's account at Customer Point(s) shall be
accomplished solely by the displacement of Gas quantities otherwise deliverable to Customer by
Pipeline pursuant to other contractual arrangements between Pipeline and Customer, and which
quantities shall be billed by Pipeline and paid by Customer as if such deliveries in fact occurred
pursuant to the relevant contractual arrangements.