Texas Eastern Transmission, L P

Seventh Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 08/13/2009, Docket: RP09-508-001, Status: Effective

Third Revised Sheet No. 613 Third Revised Sheet No. 613

Superseding: Second Revised Sheet No. 613

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

(i) Customer's existing Section 14.9 Firm Capacity

entitlements less the quantity required to meet a

valid request at the point, but not less than zero;

or

 

(ii) Customer's existing Section 14.9 Firm Capacity

entitlements, or one-hundred ten percent (110%) of

the Firm Peak Day Quantity, whichever is less.

 

(b) If the point does have an MDDO or an MDRO, as applicable, on

the exhibit(s) to the Customer's executed service agreements

under Rate Schedules CDS, FT-1, SCT, and/or SS-1, the

quantity retained will be equal to the greater of:

 

(i) Customer's existing Section 14.9 Firm Capacity

entitlements less the quantity required to meet a

valid request at the point, but not less than zero;

or

 

(ii) Customer's existing Section 14.9 Firm Capacity

entitlements, or one-hundred ten percent (110%) of

the Firm Peak Day Quantity less the MDDO or MDRO, as

applicable, but not less than zero, whichever is

less.

 

(4) For any restated quantities of Section 14.9 Firm Capacity

entitlements, Pipeline will provide to Customer written notification

informing Customer of the quantities of Section 14.9 Firm Capacity

entitlements retained at each point and the effective date of such

restated capacity, which date shall be no sooner than two (2) weeks

after Pipeline tenders such written notification. As of the

effective date of such restated capacity, Pipeline shall have no

obligation to make firm receipts and/or deliveries in excess of such

restated Section 14.9 Firm Capacity entitlements.

 

(C) Allocation of Point Capacity. Pipeline shall allocate all Remaining

Capacity under this Section 14.10 at such Point(s) of Delivery or Point(s)

of Receipt on a first-come, first-served basis based on the date and time

of the Customer's valid request for each specific point; provided, however,

that requests for new additional firm service shall have priority over

other requests. Remaining Capacity shall be uncommitted firm meter

capacity including, but not limited to, any Section 14.9 Firm Capacity

entitlements not retained by Customer(s) pursuant to Section 14.10(B). The

quantity of Remaining Capacity allocated to a Customer shall be the lesser

of the quantity requested or the Remaining Capacity at the point.