Texas Eastern Transmission, L P
Seventh Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/02/2009, Docket: RP10-30-000, Status: Effective
Original Sheet No. 573C Original Sheet No. 573C
GENERAL TERMS AND CONDITIONS
(Continued)
(iii) Pipeline determines in its sole discretion (a) that
the proposed pairing will physically occur on the
Pipeline's system within the same Monitoring Segment
as the Paired Receipts and in a way that wouild
alleviate any risk of a Liquefiable Hydrocarbon
Problem caused by the Paired Receipts and (b) that
the Paired Receipts will commingle sufficiently with
each other, assuming no other gas in Pipeline's
facilities, so that deliveries at the next downstream
delivery point will meet the Liquefiable Hydrocarbon
Limit; and
(iv) The Paired Receipts otherwise meet the specifications
in this Section 5.
(C) Pipeline shall determine whether the conditions in (B)
above are met as follows:
(i) Initial determination. After the deadline for timely
nominations for the Initial Gas Day, Pipeline shall
make a determination regarding whether the Receipt
Point operator's proposal satisfies the criteria in
subsection (B), and Pipeline will notify the Receipt
Point operator accordingly before the start of the
Initial Gas Day and shall post the Paired Points if
the proposal is approved. To the extent Pipeline
cannot determine that the pairing proposal meets all
of the above conditions in subsection (B), Pipeline
will provide a written denial specifying the basis
for its denial to the Receipt Point operator.
(ii) Daily determination. With respect to nominations for
any gas day after the Initial Gas Day, to the extent
Pipeline cannot determine that the pairing proposal
meets all of the above conditions in subsection (B),
Pipeline may suspend the pairing proposal for such
gas day.
(iii) Early submittal. Pipeline shall allow Receipt Point
operators to submit pairing proposals before a
Liquefiable Hydrocarbon Limit is issued, to be
effective in the event that such a Liquefiable
Hydrocarbon Limit is issued, but Pipeline will not be
obligated to evaluate such a proposal and reach a
decision regarding whether the proposal meets the
conditions in 5.10(B) before the deadline for timely
nominations for the Initial Gas Day.