Texas Eastern Transmission, L P

Seventh Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/16/2009, Docket: RP10-53-000, Status: Effective

Second Revised Sheet No. 399 Second Revised Sheet No. 399

Superseding: First Revised Sheet No. 399

 

RATE SCHEDULE ISS-1

(Continued)

 

5.5 Limitation Upon Total Injection Pipeline shall be obligated to accept Gas for

storage for Customer's account in accordance with the above procedure only when

Customer's Storage Inventory is less than Customer's Maximum Storage Quantity and only

to the extent Pipeline determines that such injection shall not be detrimental to

Pipeline's ability to satisfy its firm obligations under its firm rate schedules.

 

6. WITHDRAWAL PROVISIONS

 

6.1 General Procedure If Customer desires the delivery of Gas stored for Customer's

account under this Rate Schedule, it shall give notice to Pipeline specifying the

Quantity of Gas, not in excess of the MDWQ, plus Applicable Shrinkage, which Customer

desires to be withdrawn from storage under this Rate Schedule during such Day.

Subject to Section 7 of this Rate Schedule ISS-1, Pipeline shall thereupon deliver to

Customer the Quantity of Gas subject to the limitations set forth herein. The Natural

Gas delivered by Pipeline for Customer's account as a result of storage withdrawal

pursuant to this Service Agreement shall be those quantities scheduled for withdrawal

hereunder and subsequent transportation pursuant to service agreements for

transportation service between Pipeline and Customer under transactions which specify

as a Point of Receipt the "ISS-1 Storage Point". For purpose of billing under

transportation Rate Schedules, withdrawals from storage for subsequent transportation

under such transportation Rate Schedules shall be deemed to have been received 60% in

Market Zone 2 and 40% in Market Zone 3. In addition to the withdrawal of Gas from

storage for delivery through a transportation service on Pipeline's system, Gas may be

withdrawn for delivery into the facilities of third parties at the points of

interconnection between Pipeline and the facilities of such third parties at Oakford

and Leidy Storage Fields provided that such withdrawals do not result in Customer

withdrawing Gas in excess of his MDWQ or MSQ. A separate transportation charge will

not be applicable to these deliveries.

 

6.2 Notice Required The notice given by Customer to Pipeline for withdrawals on any Day

shall be in accordance with Section 4 of Pipeline's General Terms and Conditions of

this FERC Gas Tariff.

 

6.3 Limitation Upon Total Withdrawals Pipeline shall be obligated to deliver to Customer

Gas for Customer's account only when Customer's Storage Inventory is greater than zero

and only to the extent Pipeline determines that such withdrawal shall not be

detrimental to Pipeline's ability to satisfy its firm obligations under its firm rate

schedules.

 

7. PROCEDURES FOR SCHEDULING, ALLOCATION AND INTERRUPTION OF STORAGE SERVICE

 

7.1 If Customer desires to inject or withdraw Natural Gas pursuant to this Rate Schedule

ISS-1, Customer shall give notice to Pipeline in accordance with Section 4 of

Pipeline's General Terms and Conditions specifying the Quantity of Gas Customer

desires to inject or withdraw and specifying the Rate Schedule ISS-1 Transportation

Rate Schedules service agreement(s) to be utilized to accomplish the delivery of such

Gas for injection or the receipt of such Gas for withdrawal. In no event shall the

quantity to be injected or withdrawn, as applicable, exceed the Quantity of Gas

scheduled for transportation pursuant to Section 4 of Pipeline's General Terms and

Conditions under the specified Rate Schedule ISS-1 Transportation Rate Schedules

service agreement(s) to accomplish the delivery of such Gas for injection or the

receipt of such Gas for withdrawal.