Texas Eastern Transmission, L P

Seventh Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/16/2009, Docket: RP10-53-000, Status: Effective

First Revised Sheet No. 392 First Revised Sheet No. 392

Superseding: Original Sheet No. 392

 

RATE SCHEDULE FSS-1

(Continued)

 

9. IMBALANCES

 

Except to the extent Point of Receipt and Point of Delivery imbalances are reconciled and

resolved pursuant to Rate Schedule(s) TABS-1 and/or MBA, as applicable, imbalances shall

be reconciled and resolved pursuant to Section 8 of Pipeline's General Terms and

Conditions.

 

10 RATE SCHEDULES SS AND SS-1, AND ORIGINAL VOLUME NO. 2 RATE SCHEDULE X-28 CONVERSIONS

 

10.1 Those Rate Schedule SS Agreements previously entered into by Customers with Pipeline

for firm storage service and firm transportation service may be converted at any time

to Rate Schedule FSS-1 Service Agreements and Rate Schedule CDS or FT-1 Service

Agreements, at the Customer's request, if Pipeline receives such request to convert by

November 1, 1993. As of the effective date of such conversion, the rights and

obligations of the parties to the Rate Schedule SS Agreements related to firm storage

service shall be determined pursuant to this Rate Schedule FSS-1.

 

10.2 The Original Volume No. 2 Rate Schedule X-28 agreement previously entered into by

Customer with Pipeline for firm storage service may be converted at any time to a Rate

Schedule FSS-1 Service Agreement, at the Customer's request, if Pipeline receives such

request to convert by November 1, 1993. As of the effective date of such conversion,

the rights and obligations of the parties to the Original Volume No. 2 Rate Schedule X-

28 agreement shall be determined pursuant to this Rate Schedule FSS-1.

 

10.3 Those Rate Schedule SS-1 Agreements previously entered into by Customers with Pipeline

for firm storage service and firm transportation service may be converted to Rate

Schedule FSS-1 Service Agreements and Rate Schedule CDS or FT-1 Service Agreements, at

the Customer's request, if Pipeline receives such request to convert by May 3, 1993.

As of the effective date of such conversion, the rights and obligations of the parties

to the Rate Schedule SS-1 agreements related to firm storage service shall be

determined pursuant to this Rate Schedule FSS-1.

 

11. RATE SCHEDULE CD-2 CONVERSION

 

On May 31, 1993, Pipeline will transfer title to all Gas in storage to which Pipeline has

title attributable to CD-2 service to all CD-2 increment Customers for service under Rate

Schedule SS-1 or FSS-1. All Gas which has been injected by Pipeline for a Customer pursuant

to Rate Schedule CD-2, will be allocated 100% to that Customer. All remaining Gas will be

allocated on a pro rata basis. Such proration shall be determined among