Texas Eastern Transmission, L P
Seventh Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 03/14/2010, Docket: RP10-375-000, Status: Effective
Second Revised Sheet No. 388 Second Revised Sheet No. 388
Superseding: First Revised Sheet No. 388
RATE SCHEDULE FSS-1
(Continued)
(F) Excess Withdrawal Charge:
The Excess Withdrawal Charge Rate, as determined by Section 3.1 herein,
multiplied by the quantities of Excess Withdrawal Gas delivered for the Month
pursuant to the executed service agreement;
3.3 In addition to all other charges hereunder, Customers shall pay Pipeline the applicable
Incremental Facility Charge, as set forth on the Statement of Rates for Rate Schedule
FSS-1, per Month per Dth of additional MSQ, MDWQ and/or MDIQ, as applicable, for which
each Customer contracted under Pipeline's various incremental facility expansions. The
additional Dth applicable for each Customer under each applicable incremental facility
expansion are set forth on the Statement of Rates for Rate Schedule FSS-1.
3.4 Except as provided in Section 3.5 of this Rate Schedule, in the event Pipeline fails to
withdraw on any one Day at least 95% of the Quantity of Gas requested to be withdrawn
by Pipeline on such Day up to the MDWQ, the Reservation Charge shall be decreased by
the amount of the Reservation Charge Adjustment (as set forth on the Statement of Rates
for Rate Schedule FSS-1 of Pipeline's FERC Gas Tariff, Volume No. 1, as such Statement
of Rates may be revised, superseded or supplemented from time to time) multiplied by
the Quantity of Gas not withdrawn up to the lesser of the total Quantity of Gas
requested and not withdrawn, or the MDWQ. Such Reservation Charge Adjustment shall
be discounted in the case of an executed service agreement containing a discounted
Reservation Charge Rate in the same proportion such Reservation Charge Rate is
discounted from the maximum Reservation Charge Rate.
3.5 Pipeline shall not be obligated to adjust the Reservation Charge pursuant to Section
3.4 when Pipeline's failure to withdraw on any one Day at least 95% of the Quantity of
Gas requested by Customer to be withdrawn on such Day up to the MDWQ:
(A) is the result of the conduct of Customer or the downstream operator of the
facilities at the Point of Delivery;
(B) is the result of Pipeline having operational flow orders in effect on such Day;
(C) is the result, during the period from May 1 through November 1 of any year, of
Pipeline performing routine operational maintenance and repair;
(D) is the result of Pipeline performing at anytime repair and maintenance of its
facilities to comply with applicable regulatory requirements, or