Texas Eastern Transmission, L P

Seventh Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 03/14/2010, Docket: RP10-375-000, Status: Effective

Third Revised Sheet No. 272 Third Revised Sheet No. 272

Superseding: Second Revised Sheet No. 272

 

RATE SCHEDULE IT-1

(Continued)

 

3. RATE

 

3.1 The applicable rates for service hereunder in each Zone are set forth in the currently

effective Statement of Rates for Rate Schedule IT-1 of this FERC Gas Tariff and hereby

incorporated herein. The rates in this Rate Schedule are subject to adjustment

pursuant to Section 15 of Pipeline's General Terms and Conditions. Unless Pipeline

and Customer agree in writing upon a rate for service provided hereunder, the rate

applicable to a Customer for service hereunder shall be the applicable maximum rate(s)

as set forth on the effective Statement of Rates for Rate Schedule IT-1. In the event

a rate less than the applicable maximum rate(s) and not less than the applicable

minimum rate(s) is agreed upon, such rate shall be applicable for the period agreed

upon by Customer and Pipeline.

 

3.2 For Customers executing a service agreement for transportation which is not solely a

backhaul transportation arrangement, Customer shall pay Pipeline each Month a Monthly

Usage Charge consisting of the sum of the following daily charges:

 

(A) The Usage-1 Charge Rate, as determined pursuant to Section 3.1 herein, multiplied

by that portion of the total Quantity of Gas deliveries on any Day pursuant to

the executed service agreement, which is not in excess of 110% of scheduled

service levels for such Day.

 

(B) The Usage-2 Charge Rate, as set forth on the Statement of Rates for Rate Schedule

IT-1, multiplied by that portion of the total Quantity of Gas deliveries on any

Day pursuant to the executed service agreement, which is in excess of 110% of

scheduled service levels for such Day.

 

3.3 For Customers executing a service agreement for transportation which is solely a

backhaul transportation arrangement, Customer shall pay Pipeline each Month a Monthly

Usage Charge consisting of the sum of the following daily charges:

 

(A) The Usage-1 Charge Rate, as determined pursuant to Section 3.1 herein, multiplied

by that portion of the total Quantity of Gas deliveries on any Day pursuant to

the executed service agreement, which is not in excess of 110% of scheduled

service levels for such Day.

 

(B) The Usage-2 Charge Rate, as set forth on the Statement of Rates for Rate Schedule

IT-1, multiplied by that portion of the total Quantity of Gas deliveries on any

Day pursuant to the executed service agreement, which is in excess of 110% of

scheduled service levels for such Day.