RATE SCHEDULE FT-1

(Continued)

 

11. RESERVED FOR FUTURE USE

 

12. ORIGINAL VOLUME NO. 2 CONVERSIONS AND INDIVIDUAL CERTIFICATED RATE SCHEDULE CONVERSIONS

 

12.1 Those Original Volume No. 2 agreements previously entered into by Customers with

Pipeline for firm service under Rate Schedules X-43, X-74, X-79, X-80, X-88, X-89, X-

90, X-91, X-100, X-101, X-102, X-103, X-104, and X-121 may be converted at any time to

Rate Schedule FT-1 Service Agreements, at the Customer's request, if Pipeline receives

such request to convert by November 1, 1993. As of the effective date of such

conversion, the rights and obligations of the parties to the Original Volume No. 2

Agreements shall be determined pursuant to this Rate Schedule FT-1.

 

12.2 Those individual certificated rate schedule agreements previously entered into by

Customers with Pipeline for firm service under Rate Schedules FTS, FTS-2, FTS-4, FTS-5,

SS-2, excluding the storage component, (i.e. - Rate Schedule FTS-7) and SS-3, excluding

the storage component, (i.e. - Rate Schedule FTS-8) X-127, X-129, X-130, X-135, X-136

and X-137 may be converted at any time to Rate Schedule FT-1 Service Agreements, at the

Customer's request, if Pipeline receives such request to convert by November 1, 1993,

subject to (1) Pipeline's receipt of any necessary authorization as required by the

Commission, (2) such Customer's agreement to continue to pay Pipeline an incremental

surcharge for such service in order for Pipeline to fully recover its approved cost of

service. As of the date Pipeline receives any necessary authorization as required by

the Commission, the rights and obligations of the parties to the individual

certificated rate schedule agreements shall be determined pursuant to this Rate

Schedule FT-1.

 

13. RATE SCHEDULES DCQ, GS, CD-1, CD-2, SGS AND SS-1 CONVERSIONS

 

Customers under former Rate Schedules DCQ, GS, CD-1, CD-2 and SGS and Customers under Rate

Schedule SS-1 may enter into an FT-1 Service Agreement for any level of firm transportation

service up to such Customer's MDQ and/or MDWQ (adjusted for storage) formerly provided under

those Rate Schedules as of May 31, 1993.

 

14. GENERAL TERMS AND CONDITIONS

 

All of the General Terms and Conditions of Pipeline's FERC Gas Tariff of which this Rate

Schedule is a part are applicable to this Rate Schedule and are made a part hereof to the

extent that such terms and conditions are not contradicted by any provision herein.