Texas Eastern Transmission, L P

Seventh Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 05/01/2008, Docket: RP99-480-021, Status: Effective

Original Sheet No. 119 Original Sheet No. 119 : Effective

 

 

STATEMENT OF NEGOTIATED RATES 1/ 2/

 

Customer Name: Glenwood Energy of Oxford, Inc.

Contract Number: 910642 3/

Rate Schedule: SCT

Reservation Charges: The reservation charges to be paid by Customer each month during the

Negotiated Rate Term shall be the sum of (1) all maximum applicable reservation charges

under Pipeline's Rate Schedule SCT multiplied by the Applicable Billing Determinants

pursuant to Pipeline's Rate Schedule SCT and (2)(i) for each six-month period beginning

each May and extending through October, an additional monthly reservation charge equal to

$1.613 multiplied by the MDQ specified in Contract No. 910642 and (ii) for each six-month

period beginning each November and extending through April, an additional monthly

reservation charge equal to $3.226 multiplied by the MDQ specified in Contract No. 910642.

Demand Charge: The demand charge to be paid by Customer each month during the Negotiated Rate

Term shall be the demand charge rate pursuant to Pipeline's Rate Schedule SCT multiplied by

the MDQ specified in Contract No. 910642.

Usage Charges: The usage charges to be paid by Customer during the Negotiated Rate Term shall

be the maximum applicable usage charges under Pipeline's Rate Schedule SCT multiplied by

the applicable quantities of gas, in Dekatherms, delivered in the month at the point(s) of

delivery pursuant to Rate Schedule SCT, as applicable. Customer shall also pay the

applicable Annual Charge Adjustment ("ACA"), Applicable Shrinkage Adjustment ("ASA")

charges and other charges/surcharges applicable to Customer's Contract No. 910642 under

Rate Schedule SCT. Pipeline shall apply the ASA charge for service under Contract No.

910642 as such charge may change from time to time in accordance with the Commission

approved mechanism (if any) for tracking such amounts, and Customer shall pay Pipeline for

all such ASA charges.

Term of Negotiated Rate: The term of this Negotiated Rate extends from 5/1/2008 and continues

for 3 years through 4/30/2011 (the "Negotiated Rate Term"). Following the Negotiated Rate

Term, all Reservation Charges, Demand Charges and Usage Charges shall be determined

pursuant to Pipeline's Rate Schedule SCT and the additional reservation charges referred to

in paragraphs (2)(i) and (2)(ii), above, will no longer be applicable.

Maximum Daily Quantity (MDQ): 5,236 dth/d

Receipt Point(s): All points on Pipeline's Master Receipt Point List, as revised and

published by Pipeline from time to time.

Delivery Point(s): M&R 70907

Recourse Rate(s): The Recourse Rate(s) applicable to this service is the maximum rate(s) stated

for Rate Schedule SCT in Pipeline's currently effective FERC Gas Tariff.

 

1/ Upon Commission approval of this negotiated rate, Pipeline agrees not to seek recovery from

Customer of any outstanding charges related to Contract No. 800058 prior to April 1, 2008.

 

2/ The negotiated rate is applicable for receipts and deliveries at any receipt and delivery

point on Pipeline's system within each applicable zone.

 

3/ The designated service agreement does not deviate in any material respect from the Form of

Service Agreement contained in Pipeline's Tariff.