U S G Pipeline Company
ORIGINAL VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/01/2000, Docket: CP99-211-001, Status: Effective
Original Sheet No. 27 Original Sheet No. 27 : Effective
GENERAL TERMS AND CONDITIONS
4.5 Correction of metering errors - failure of meters: In the event a
meter is out of service or registering inaccurately, the volume of
gas delivered shall be determined:
(a) by using the registration of any check meter or meters, if
installed and accurately registering; or, in the absence of
(a);
(b) by correcting the error if the percentage of error is
ascertainable by calibration, tests, or mathematical
calculation; or, in the absence of both (a) and (b), then;
(c) by estimating the quantity of delivery by deliveries during
periods under similar conditions when the meter was registering
accurately.
4.6 Correction of metering errors - adjustments: A measurement data
correction shall become a prior period adjustment (PPA) after the
fifth (5th) business day following the delivery month. Measurement
data corrections shall be processed within six (6) months from the
delivery month, unless (i) Transporter and Shipper mutually agree
otherwise or (ii) the correction is the result of a deliberate
omission or misrepresentation by a Party or a mutual mistake of fact.
In all instances where a correction is made, Shipper or Transporter,
as applicable, has 90 days to dispute the correction. In the case of
corrections made under (i) or (ii) above, the period for resolving
corrections will be tolled until the correction is settled.
4.7 Preservation of metering records: Transporter and Shipper shall each
preserve for a period of at least one year all test data, charts and
other similar records.