Southern LNG Inc.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 03/01/2002, Docket: RP02-129-004, Status: Effective
Original Sheet No. 105A Original Sheet No. 105A : Effective
GENERAL TERMS AND CONDITIONS(Continued)24.3Maintenance Dredging
Cost AdjustmentThis section of the GT&C sets forth the
procedures to reflect changes in the amounts incurred by
Southern LNG for maintenance dredging of the turning basin at
the Elba Island Terminal.(a)Definitions(i)Maintenance Dredging
– The work required to maintain the required depth and
integrity of the turning basin, channel and berths at the Elba
Island Terminal, including the costs of disposing of spoil
associated with such work.(ii)Maintenance Dredging Annual
Period – The annual period beginning on March 1, 2002, and
each annual period thereafter.(iii)Maintenance Dredging Costs
– The cost for Maintenance Dredging.(iv)Actual Maintenance
Dredging Costs – The actual cost incurred by Southern LNG for
Maintenance Dredging. Such actual cost shall include all
charges attributable to any period encompassed by the
effectiveness of this Section 24.3, including all refunds,
surcharges, billing adjustments and interest, positive or
negative. (v)Estimated Maintenance Dredging Costs – The
projected Maintenance Dredging Costs for the Maintenance
Dredging Annual Period.(vi)Estimated Reservation Charge
Billing Determinants – The projected annual reservation charge
billing determinants, which shall not be less than 49,008,000
Dth of MSQ. (vii)Deferral Period – The period of 12 months
ending December 31 prior to the beginning of each Maintenance
Dredging Annual Period.(viii)Affected Rate Schedules –
Affected Rate Schedules shall be Rate Schedules LNG-1 and
LNG-2.(b)Filing Procedure(i)The Dredging Surcharge set forth
on the rate sheets of Southern LNG’s Tariff shall be increased
or be decreased as set forth in this Section 24.3.