Southern LNG Inc.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/01/2005, Docket: RP05-395-000, Status: Effective
First Revised Sheet No. 67 First Revised Sheet No. 67 : Effective
Superseding: Original Sheet No. 67
GENERAL TERMS AND CONDITIONS
(Continued)
12.6 Delivery Point Allocation:
(a) Use of PDAs:
On a daily basis at the Delivery Point, Southern LNG shall allocate the quantities of
gas metered at the point among the quantities of gas scheduled at the point for the
account of its Customers, based on the Pro Rata PDA method unless another PDA method
is provided by the party that owns or operates the downstream facilities
interconnecting with Southern LNG's facilities at the Delivery Point (the "downstream
operator"). The alternative PDA methodologies from which the downstream operator may
choose include the Swing PDA, a Ranked PDA, a Percentage PDA, or any other mutually
agreeable allocation methodology. A new allocation detail may be needed when a
nomination changes. The PDA shall be provided by the downstream operator on a line
item basis at the level of nomination detail provided by Southern LNG for
confirmation. Southern LNG shall then use the predetermined priority provided by
Customer in its nomination for applying the PDA to the Package ID level within the
line item nomination level. Customer agrees that Southern LNG shall have the right to
rely conclusively on the PDA provided pursuant to this Section 12 for the purposes of
determining the daily quantities of gas delivered by Southern LNG for the account of
Customer at each Delivery Point. Downstream operators should communicate to the other
customers that their transaction(s) for allocation purposes are lowest ranked or
swing, when such customers' transaction(s) are identified by the downstream operator
in the PDA statement submitted to Southern LNG as being lowest ranked or swing (NAESB
2.3.63).
(b) PDA Deadlines:
Each PDA must be submitted to Southern LNG, by facsimile machine or through SoNet
during the confirmation of that day's nominations or after confirmation but prior to
start of Gas Day; provided that any revisions to the PDA may be made by the downstream
operator during the confirmation period on the day of flow for intraday nomination
changes. If there are no additions in nominations by a Customer at the Delivery Point
or other changes, the current PDA will stay in effect as submitted until it is changed
pursuant to the foregoing procedures. A new allocation detail may be needed when a
nomination changes. In the event Customer adds a nomination at the Delivery Point,
then Southern LNG must provide, or cause to be provided, as set forth above, a PDA at
the Delivery Point which recognizes Customer's nomination.