Southern LNG Inc.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 03/01/2010, Docket: RP10-271-000, Status: Effective
Original Sheet No. 60E Original Sheet No. 60E
GENERAL TERMS AND CONDITIONS
(Continued)
(3) Interim Restoration Report. If Electing Customer provides Southern
LNG no later than fifteen (15) days after receiving an Interim
Restoration Report with Electing Customer's Notice of disagreement,
then Southern LNG and Electing Customer hereby agree to refer such
disagreement to a single, independent expert qualified to review and
dispose of issues with respect to the estimated cost and duration.
No later than thirty (30) days following the later of the Interim
Restoration Report or the referral, the expert shall issue a
decision in writing to Southern LNG and Electing Customer to resolve
the disagreement by selecting the more accurate of the cost and
duration estimates between the Interim Restoration Report and
Electing Customer's Notice ("Interim Expert Decision"). Southern LNG
and Electing Customer hereby agree to waive any and all challenges
to the Interim Expert Decision, which shall be preclusive for
purposes of the rights and obligations set out in Section 8.6(b)(2)
above.
(d) Abandonment
A Customer exercising its right herein to terminate its Service Agreement
shall not challenge, directly or indirectly, any application by Southern
LNG to abandon capacity associated with such firm service.