Southern LNG Inc.

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 03/01/2010, Docket: RP10-271-000, Status: Effective

Original Sheet No. 60D Original Sheet No. 60D

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

(c) Dispute Resolution:

 

(1) Initial Restoration Report. If Electing Customer provides Southern

LNG no later than thirty (30) days after receiving the Initial

Restoration Report with notice in writing that Electing Customer

disagrees with the cost and/or duration estimated in the Initial

Restoration Report and believes either the estimated cost to be

higher than the Available Funds or the estimated duration to be

longer than sixty (60) months, such disagreement to be based on

substantial evidence included with the notice along with Electing

Customer's estimate of the cost and duration ("Electing Customer's

Notice"), then Southern LNG and Electing Customer hereby agree to

refer such disagreement to a single, independent expert qualified to

review and dispose of issues with respect to the estimated cost and

duration. No later than sixty (60) days following the later of the

Initial Restoration Report or the referral, the expert shall issue a

decision in writing to Southern LNG and Electing Customer to resolve

the disagreement by selecting the more accurate of the cost and

duration estimate between the Initial Restoration Report and

Electing Customer's Notice ("Initial Expert Decision").

 

(2) Supplemental Restoration Report. Southern LNG and Electing Customer

hereby agree to refer the Supplemental Restoration Report to a

single, independent expert qualified to review and dispose of issues

with respect to the estimated cost and duration. If reasonably

available, the expert issuing the Initial Expert Decision shall be

used. No later than thirty (30) days following the later of the

Supplemental Restoration Report or the referral, the expert shall

issue a decision in writing to Southern LNG and Electing Customer

either affirming or denying the reasonableness of the Supplemental

Restoration Report ("Supplemental Expert Decision").