(a) first notice 48 hours before Customer's vessel departs the port of origin.

At that time Southern LNG will notify Customer if Southern LNG may schedule

the arrival of Customer's vessel at the date and hour stated in Customer's

notice. If Southern LNG agrees to schedule the arrival of Customer's vessel,

then Southern LNG will issue a scheduling notice to Customer stating the

quantity of Customer's LNG Balance that Customer must nominate for

vaporization and delivery in order to accommodate the quantities of LNG

stated in Customer's notice for receipt by Southern LNG.

 

(b) second notice when Customer's vessel departs the port or origin;

 

(c) third notice for receipt by Southern LNG 96 hours before estimated arrival;

 

(d) fourth notice for receipt by Southern LNG 72 hours before estimated arrival;

 

(e) fifth notice for receipt by Southern LNG 48 hours before estimated arrival;

 

(f) sixth notice for receipt by Southern LNG 24 hours before estimated arrival;

 

(g) seventh notice for receipt by Southern LNG 5 hours before estimated arrival;

 

(h) final notice when Customer's vessel enters the channel of the Savannah

River.

 

5.2 Scheduling Priorities for the Receipt of LNG from Customer's Vessel(s):

 

If all requests for the receipt of LNG from Customers' vessel(s) cannot be

scheduled, and all conflicts in the arrival of Customers' vessels cannot be

resolved by mutual agreement among Southern LNG and the affected Customers, then

Southern LNG shall schedule service in the following order:

 

(i) Firm Service in sequence starting with the highest rate for service;

 

(ii) Interruptible Service in sequence starting with the highest rate for

service;

 

If two or more Customers have the same priority using the above criteria, service

will be scheduled in sequence starting with the earliest executed Service Agreement

currently in effect.

 

5.3 Unscheduled Arrival:

 

If Customer's vessel does not arrive as scheduled pursuant to section 5.1(a) of

this Rate Schedule, then Southern LNG shall receive the LNG from the unscheduled

vessel at the first time available without causing detriment to any scheduled Firm

Service, without regard for whether the unscheduled arrival is the result of

Customer's force majeure. Customer agrees to reimburse Southern LNG for all costs

incurred as a result of the vessel's failure to arrive as scheduled.