Southern LNG Inc.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 03/01/2010, Docket: RP10-271-000, Status: Effective
First Revised Sheet No. 28 First Revised Sheet No. 28
Superseding: Original Sheet No. 28
RATE SCHEDULE LNG-2
(Continued)
5.9 Increase in LNG Balance
Customer's LNG Balance will be increased for each nomination cycle set out in the General Terms
and Conditions by the quantity of LNG received by Southern LNG for Customer's account by that
nomination cycle. The quantity received by Southern LNG for Customer's account shall not
include the amount of boil-off returning to Customer's vessel(s) during unloading of LNG.
6. STORAGE WITHDRAWALS AND DELIVERIES
Southern LNG delivers vaporized LNG at the pipeline interconnects on Elba Island.
6.1 Delivery of Vaporized LNG:
(a) Nomination Threshold; Minimum Inventory:
Nothing in this Tariff shall obligate Southern LNG to schedule deliveries of vaporized
LNG on any day unless aggregate nominations by all Customers for delivery on that day
exceed 75,000 Dth.
Nothing in this Tariff shall obligate Southern LNG to deliver vaporized LNG when such
delivery would cause the total inventory of LNG in Southern LNG's storage tanks to
decline to or below the tank heel.
(b) Uniform Hourly Vaporization Quantity:
Subject to GT&C §§ 8.3 and 8.4, and any interruption of service, Southern LNG shall
withdraw, vaporize, and deliver Customer's scheduled quantity at a uniform hourly rate
up to one twenty-fourth (1/24) of its scheduled quantity.
If Customer requests, Southern LNG shall endeavor, as operating conditions permit, to
deliver vaporized LNG at greater than the uniform hourly rate.