5. RECEIPT OF LNG FROM CUSTOMER'S VESSEL(S)
Southern LNG receives LNG at the vessel unloading facilities on Elba Island, Georgia.
5.1 Customer shall give, or cause to be given, to Southern LNG notice by electronic mail prior to
each receipt by vessel. Southern LNG will provide Customer(s) with the manner in which
Southern LNG must receive notice. The notice shall identify Customer(s) vessel (from among the
vessels specified in Customer's Service Agreement) and state the date and hour of arrival at
the terminal and the quantity of LNG to be received by Southern LNG. Customer shall send
notice as follows:
(a) first notice 48 hours before Customer's vessel departs the port of origin. At that
time Southern LNG will notify Customer if Southern LNG may schedule the arrival of
Customer's vessel at the date and hour stated in Customer's notice. If Southern LNG
agrees to schedule the arrival of Customer's vessel, then Southern LNG will issue a
scheduling notice to Customer stating the quantity of Customer's LNG Balance that
Customer must nominate for vaporization and delivery in order to accommodate the
quantities of LNG stated in Customer's notice for receipt by Southern LNG.