Phillips Gas Pipeline Company

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: / / , Docket: RS92- 47-001, Status: Effective

Original Sheet No. 70 Original Sheet No. 70 : Superseded

 

 

1.2 The Firm Transportation Quantity stated above shall be subject to

reduction by PGPL from time to time pursuant to the then effective

provisions of Rate Schedule FT-1.

 

1.3 Exhibit A attached hereto and incorporated by reference herein states

the Point(s) of Receipt and Redelivery. Exhibit A may be amended

only by written agreement between the parties.

 

 

ARTICLE 2 - TERM

 

2.1 This Agreement shall be effective from the date first stated above and

shall remain effective through a primary term of _________________

and thereafter shall continue in effect until terminated by PGPL or

Shipper upon at least thirty (30) days prior notice to the other.

 

2.2 Notwithstanding the prior provisions of this Article 2, PGPL shall have

the right to terminate service hereunder (1) if 18 C.F.R., Part 284

Subpart B of the Regulations of the Federal Energy Regulatory

Commission or successor agency (Commission) effective on the date

first stated above, is stayed, modified or overturned by an appellate

court or by the Commission, (2) if PGPL terminates self-implementing

transportation pursuant to Section 311 of the Natural Gas Policy Act

of 1978 on a general, non-discriminatory basis, or (3) pursuant to any

effective provisions for termination of this Agreement by PGPL as

stated in Rate Schedule FT-1 or the General Terms and Conditions

for Transportation Service.

 

 

 

ARTICLE 3 - RATES AND CHARGES

 

3.1 For the services provided or contracted for hereunder, Shipper agrees

to pay PGPL the then-effective, applicable rates and charges under

PGPL's Rate Schedule FT-1 filed with the Commission, as such rates

and charges and Rate Schedule FT-1 may hereafter be modified,

supplemented superseded, or replaced generally or as to the service

hereunder. PGPL reserves the unilateral right from time to time to

file and to make effective any such changes in the terms of rate levels

under Rate Schedule FT-1 and the applicability thereof, the General

Terms and Conditions for Transportation Service or any other

provisions of PGPL's Tariff, subject to the applicable provisions of the

Natural Gas Act and the Commission's Regulations thereunder.