Midwest Gas Storage, Inc.
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/15/1994, Docket: CP90-454-004, Status: Effective
Original Sheet No. 105 Original Sheet No. 105 : Effective
Schedule FSS. Such short-term releases need not
comply with the notification and bidding
requirements of this Section 8; however, they
may not be rolled over, extended, or in any way
continued without first being subjected to the
notification and bidding process set forth in
this Section 8, nor may this capacity be re-
released to the same Replacement Shipper until
thirty (30) days after the first release period
has ended.
(c) Potential Replacement Shippers may post on
Midwest's EBB a notice requesting released FSS
capacity. Such notices will be posted for the
length of time specified in the notice; however,
in no event will such notices be posted for
longer than one month.
(d) Releasing Shipper shall be subject to the
provisions of Section 4 of this Rate Schedule
prior to the commencement of the Agreement with
Replacement Shipper.
8.3 PROCEDURE FOR REQUESTING TO RELEASE CAPACITY:
(a) Contents of Release Notice: Releasing Shipper
shall provide Midwest with a notice in writing
or on Midwest's electronic bulletin board
requesting to release capacity for resale and
shall state in such notice the following items:
(i) the pricing provisions of the proposed
release, subject to the limits of the
Midwest's maximum and minimum rates,
(ii) the specific quantity to be released at
each receipt and delivery point,
(iii) the duration of release,
(iv) length of bid period, if Midwest's default
bidding period is not to be used,