Pine Needle LNG Company, LLC

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 02/27/2005, Docket: RP05-167-000, Status: Effective

Second Revised Sheet No. 55 Second Revised Sheet No. 55 : Effective

Superseding: Original Sheet No. 55

GENERAL TERMS AND CONDITIONS

(Continued)

 

12. PRESSURES

 

Deliveries of natural gas to Pine Needle at the Point of Receipt shall be made at sufficient

pressures to enter Pine Needle's system but in no event shall Pine Needle receive such

deliveries at pressures higher than 800 psig.

 

Pine Needle shall deliver natural gas to Customer or Customer's transporter at sufficient

pressures at the Point of Delivery to enter the downstream transporter's system but in no

event shall Pine Needle make such deliveries at pressures greater than 800 psig.

 

Natural gas delivered by Pine Needle to Customer or Customer's transporter in the liquid

phase shall be at the pressure developed by the force of gravity on the liquid head contained

in Pine Needle's storage tank or at the pressure developed by auxiliary equipment that may be

in operation at the time of delivery.

 

 

13. DULY CONSTITUTED AUTHORITIES

 

The rate schedules of Pine Needle, these General Terms and Conditions, and the respective

obligations of the parties under the service agreements, are subject to valid laws, orders,

rules and regulations of duly constituted authorities having jurisdiction.

 

 

14. NOTICES

 

Except as otherwise provided in this FERC Gas Tariff or in the executed service agreement,

any notice, request, demand, statement or bill which either Pine Needle or Customer may

desire to give to the other, shall be in writing and shall be considered as duly delivered

when mailed by postpaid registered mail addressed to said party at its last known postoffice

address, or at such other address as either party may designate in writing. Routine

communications, including monthly statements and payments, shall be considered as duly

delivered when mailed by either registered or ordinary mail. General communications will be

posted on Pine Needle's electronic bulletin board (Pine Needle's EBB) and such posting shall

be considered as duly delivered.

 

 

15. MAXIMUM DAILY DELIVERY OBLIGATIONS

 

The maximum daily delivery obligation under Pine Needle's Rate Schedule LNG-1 or LNG-R shall

be the Vaporization Quantity specified in the applicable service agreement. Pine Needle shall

notify Customer, in advance, of the Heating Value to be used by Customer to determine the

maximum daily delivery obligation of Pine Needle and, as far in advance as possible, when any

change in such Heating Value is anticipated.