First Revised Sheet No. 53 First Revised Sheet No. 53 : Effective
Superseding: Original Sheet No. 53
GENERAL TERMS AND CONDITIONS
(Continued)
11. FORCE MAJEURE AND OPERATING CONDITIONS (Continued)
11.1 Definition of Force Majeure and Operating Conditions (Continued)
Such causes or contingencies affecting the performance by either party, however, shall
not relieve it of liability unless such party shall give notice and full particulars
of such cause or contingency in writing, facsimile, telephone or through electronic
means to the other party within a reasonable time after the occurrence relied upon,
nor shall such causes or contingencies affecting the performance by either party
relieve it of liability in the event of its failure to use due diligence to remedy the
situation and remove the cause with all reasonable dispatch, provided that the
resolution of strikes, lockouts or other labor disputes shall be within the sole
discretion of the party involved therein. Such causes or contingencies affecting the
performance of either party shall not relieve Customer from (i) its obligation to make
payments of daily demand charges except to the extent that such causes or
contingencies are caused by Pine Needle's negligence or willful misconduct, and (ii)
its obligation to make payment of amounts accrued and due at the time thereof.
11.2 Daily Interruption or Allocation of Services Due to Force Majeure or Unscheduled
Operating Conditions
(a) If, due to force majeure or unscheduled operating conditions, Pine Needle is
unable to receive, liquefy, vaporize or redeliver gas tendered by Customers for
firm contract storage service, then Pine Needle, shall order reduction of service
in accordance with the following provisions:
(i) In cases where Pine Needle's ability to provide service under Rate Schedule
LNG-2 is affected, Pine Needle shall first order interruption or allocation
of service on a last-come-first-interrupted basis.
(ii) After interruption or allocation of services as specified in 11.2(a)(i)
above, Pine Needle shall order reduction of Customers' firm contract
storage, liquefaction and/or vaporization entitlements on a pro rata basis
based on firm contract entitlements.