19. RECEIPT AND DELIVERY FACILITIES
19.1 General. This section applies only to those receipt or delivery
facilities contemplated by Section 1(b) of Rate Schedules FT-1
and Section 1(a) of Rate Schedule IT-1 needed to accommodate customer
requests. This section does not apply to receipt or delivery facilities
constructed by Transporter to accommodate new transportation commitments
solicited by Transporter through an open season. This section is not
intended to limit who may own, operate, install or pay for facilities
upstream of a Receipt Point or downstream of a Delivery Point. It is
the Shipper's responsibility to assure that all facilities installed and
owned by Shipper or any other third party upstream of a Receipt Point or
downstream of a Delivery Point comply with all applicable governmental
regulations and design requirements for their intended use (i.e.,
pressure, control, etc.).
19.2 Construction, Operation, and Ownership.
(a) Consistent with the Agreement for the Ownership, Construction
and Operation of the Kelso Beaver Pipeline (see Preliminary
Statement) Transporter will construct, own, operate and maintain
receipt and delivery facilities unless otherwise agreed to in writing
by Transporter and Shipper. Regardless, Transporter will install,
own and operate all taps and related valves or check valves on its
transmission lines. Facilities to be constructed or modified may
not compromise the operational integrity of Transporter's
transmission system or transportation entitlements of others, and
construction is subject to acquiring necessary regulatory approvals.
(b) For any receipt or delivery facilities to be constructed by
Shipper, Shipper will coordinate construction of such facilities
with Transporter so that Transporter may reasonably have
inspectors at the site during construction. All such facilities
must include any rights-of-way necessary to access facilities for
inspection and maintenance. Any such facilities constructed by
Shipper must be in accordance with Transporter's specifications.
Transporter must approve related design drawings and bills of