9. FORCE MAJEURE
Neither Transporter nor Shipper shall be liable in damages to the
other for any act, omission or circumstance occasioned by or in
consequence of any actual or threatened blockades, insurrections, riots,
epidemics, flood, washouts, landslides, mudslides, earthquakes, extreme
cold or freezing weather, lightning, rulers and peoples, civil
disturbances, explosions, breakage or imminent breakage or freezing of
or accident to machinery or line of pipe, the order of any court or
governmental authority having jurisdiction, required maintenance of
facilities, labor disturbances, and any other cause, whether of the kind
herein enumerated or otherwise, not reasonably within the control of the
party claiming suspension and which by the exercise of due diligence such
party is unable to prevent or overcome. Failure to prevent or settle any
strike or strikes shall not be considered a matter within the control of
the party claiming suspension.