9. FORCE MAJEURE

 

Neither Transporter nor Shipper shall be liable in damages to the

other for any act, omission or circumstance occasioned by or in

consequence of any actual or threatened blockades, insurrections, riots,

epidemics, flood, washouts, landslides, mudslides, earthquakes, extreme

cold or freezing weather, lightning, rulers and peoples, civil

disturbances, explosions, breakage or imminent breakage or freezing of

or accident to machinery or line of pipe, the order of any court or

governmental authority having jurisdiction, required maintenance of

facilities, labor disturbances, and any other cause, whether of the kind

herein enumerated or otherwise, not reasonably within the control of the

party claiming suspension and which by the exercise of due diligence such

party is unable to prevent or overcome. Failure to prevent or settle any

strike or strikes shall not be considered a matter within the control of

the party claiming suspension.