Original Sheet No. 37 Original Sheet No. 37 : Effective
GENERAL TERMS AND CONDITIONS
(Continued)
4. MEASUREMENT OF GAS (Continued)
(c) by estimating the quantity of deliveries by comparison with
deliveries during preceding periods under similar conditions when
the meter was registering accurately.
4.9 Correction of Volume Calculation Error. If, upon inspection and
verification, any volume calculation error shall result in a daily
volume inaccuracy exceeding two (2) percent, then the inaccuracy shall
be corrected to zero error following verification by Transporter and
Shipper, however, in no event shall inaccuracies less than two (2)
percent daily or 100 Dth monthly be corrected.
4.10 Prior Period Adjustments. For treatment of measurement prior period
adjustments, treat the adjustment by taking it back to the production
month. A meter adjustment becomes a prior period adjustment after the
fifth business day following the business month. (NAESB 2.3.11)
4.11 Records Preservation. Each party shall preserve all test and
measurement data, charts or similar records for a period of at least
one (1) year or such other periods as shall be required under Part 225
of the Commission's regulations or the lawful requirements of any other
governmental body, Federal or State, prescribing longer retention
periods for any category of record.