33. CONSTRUCTION OF NEW RECEIPT OR DELIVERY FACILITIES

 

33.1 All requests for new interconnections must be made in writing. A

party requesting the new interconnection shall reimburse Saltville

or cause Saltville to be reimbursed for any and all reasonable

costs and expenses incurred in constructing, establishing or

modifying the facilities required to establish a new

interconnection on existing facilities for receipt or delivery of

Gas hereunder. In the alternative, the party requesting the

interconnection may perform the construction at its own cost in

compliance with Saltville's technical requirements. In addition

to the above requirements, Saltville will agree to construct a new

interconnection or modify an existing interconnection on the

following terms:

 

(a) The construction of the new interconnection will not create

any significant operational problems for Saltville;

 

(b) The proposed interconnection will not adversely affect the

rendition of existing service or adversely alter the

operation of the pipeline system;

 

(c) The new interconnection must be at a mutually agreeable

location on the Saltville system; provided, however, that

Saltville may not deny a Customer's request for specific

placement of the interconnection without adequate

operational, environmental, or legal justification;

 

(d) In order to properly and prudently design and size the new

interconnection, Saltville must be provided with reasonable

and reliable data concerning the interconnecting facilities,

including delivery pressures, and anticipated hourly, daily,

monthly and annual volume levels of the service that

supports the new interconnection and such other data as is

reasonably required to construct the interconnection

facility;

 

(e) The new interconnection must not result in any minimum

pressure receipt or delivery requirement by Saltville unless

Saltville agrees otherwise, such agreement shall not be

unreasonably withheld, and Saltville shall not be

responsible for any downstream parties' facilities, the

operation or maintenance of such facilities, or the delivery

of any unauthorized volumes to the facilities;

 

(f) The service supporting the interconnection as well as the

construction of the new facilities must conform to the

provisions of Saltville's currently effective FERC Gas

Tariff, as well as applicable regulatory requirements;

 

(g) The proposed interconnection must not cause Saltville to be

in violation of any applicable environmental or safety laws

or regulations with respect to the facilities required to

establish an interconnection with Saltville's existing

facilities; and

 

(h) The proposed interconnection must not cause Saltville to be

in violation of its right-of-way agreements or any other

contractual obligations with respect to the interconnection

facilities.