33. CONSTRUCTION OF NEW RECEIPT OR DELIVERY FACILITIES
33.1 All requests for new interconnections must be made in writing. A
party requesting the new interconnection shall reimburse Saltville
or cause Saltville to be reimbursed for any and all reasonable
costs and expenses incurred in constructing, establishing or
modifying the facilities required to establish a new
interconnection on existing facilities for receipt or delivery of
Gas hereunder. In the alternative, the party requesting the
interconnection may perform the construction at its own cost in
compliance with Saltville's technical requirements. In addition
to the above requirements, Saltville will agree to construct a new
interconnection or modify an existing interconnection on the
following terms:
(a) The construction of the new interconnection will not create
any significant operational problems for Saltville;
(b) The proposed interconnection will not adversely affect the
rendition of existing service or adversely alter the
operation of the pipeline system;
(c) The new interconnection must be at a mutually agreeable
location on the Saltville system; provided, however, that
Saltville may not deny a Customer's request for specific
placement of the interconnection without adequate
operational, environmental, or legal justification;
(d) In order to properly and prudently design and size the new
interconnection, Saltville must be provided with reasonable
and reliable data concerning the interconnecting facilities,
including delivery pressures, and anticipated hourly, daily,
monthly and annual volume levels of the service that
supports the new interconnection and such other data as is
reasonably required to construct the interconnection
facility;
(e) The new interconnection must not result in any minimum
pressure receipt or delivery requirement by Saltville unless
Saltville agrees otherwise, such agreement shall not be
unreasonably withheld, and Saltville shall not be
responsible for any downstream parties' facilities, the
operation or maintenance of such facilities, or the delivery
of any unauthorized volumes to the facilities;
(f) The service supporting the interconnection as well as the
construction of the new facilities must conform to the
provisions of Saltville's currently effective FERC Gas
Tariff, as well as applicable regulatory requirements;
(g) The proposed interconnection must not cause Saltville to be
in violation of any applicable environmental or safety laws
or regulations with respect to the facilities required to
establish an interconnection with Saltville's existing
facilities; and
(h) The proposed interconnection must not cause Saltville to be
in violation of its right-of-way agreements or any other
contractual obligations with respect to the interconnection
facilities.