Saltville Gas Storage Company L.L.C.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 01/01/2009, Docket: RP09-71-001, Status: Effective
Sub Fourth Revised Sheet No. 119 Sub Fourth Revised Sheet No. 119
Superseding: Fourth Revised Sheet No. 119
GENERAL TERMS AND CONDITIONS
(Continued)
4.6 Bidding and Selection of Replacement Customer. All bids must
contain the applicable information required in this Section 4. If
Releasing Customer desires to solicit bids for releases of 31 days
or less, it may direct Saltville to post notice of the
availability of such capacity and, in lieu of permitting bids
during the otherwise applicable posting period, award the capacity
to the bidder which submits first in time a valid bid meeting any
minimum terms specified by the Releasing Customer. For releases
that become effective on or after July 30, 2008, Replacement
Customers may submit bids in excess of the maximum tariff rate for
the applicable service if (i) the term of the proposed release is
one (1) year or less, and (ii) the effective date of the proposed
release is on or before one (1) year from the date on which
Saltville is notified of the release. Such rate will be utilized
in the determination of the "best bid." Any bid submitted by a
Replacement Customer shall include an e-mail address for at least
one contact person and it is Customer's responsibility to update
e-mail address information provided to Saltville, as necessary.
Any contingencies included in the bid shall not be contrary to any
applicable provision of this FERC Gas Tariff. A bidder may not
have more than one eligible bid for the same release offer at any
time. Bids shall be binding until written or electronic notice of
withdrawal is received by Saltville before the end of the bid
period. Bids cannot be withdrawn after the bid period ends. Once
a bid is withdrawn, that bidder may only submit a new bid pursuant
to that release offer if it is at a higher rate than the withdrawn
bid. Saltville shall evaluate the bids in accordance with the
provisions of Section 4.7 herein and shall determine the best bid
in accordance with the timelines set forth in Section 4.3 herein.
Saltville shall not award capacity release offers to the
Replacement Customer until and unless the Replacement Customer
meets Saltville's creditworthiness requirements applicable to all
services that it receives from Saltville, including the service
represented by the capacity release. Saltville shall notify
Releasing Customer, the best bidder, and any Prearranged Customer
of such determination in accordance with the timelines set forth
in Section 4.3 herein. If there is a Prearranged Customer, such
Prearranged Customer may exercise its right to match such best bid
by providing notice of such exercise to Saltville via the LINK®
System in accordance with the timelines set forth in Section 4.3
herein. After the Replacement Customer is selected, Saltville
will provide an appropriate Addendum to the Capacity Release
Umbrella Agreement in the form contained in this FERC Gas Tariff
to the Replacement Customer via e-mail, at which time the
Replacement Customer will have the same rights and obligations as
any other existing Customer on Saltville's system, including
capacity release under this Section 4, subject to the re-release
rights specified by Releasing Customer pursuant to Section 4.1(s)
above. Saltville will notify the Releasing Customer with recall
rights of the name of new Replacement Customers who subsequently
obtain all or a portion of such capacity after the Addendum to the
Capacity Release Umbrella Agreement is tendered. Following
implementation of the release, Saltville shall post notice of the
winning bidder on the LINK® System.