Natural Gas Pipeline Company Of America
Seventh Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/18/2008, Docket: RP08-319-000, Status: Effective
Original Sheet No. 497 Original Sheet No. 497 : Pending
GENERAL TERMS AND CONDITIONS
----------------------------
(h) OTHER CONSENTING CUSTOMERS
Other Consenting Customers shall mean Associated
Natural Gas Company and City of Nebraska City, Nebraska, which are
former DMQ-1 sales customers which are not part of the Natural
Customer Group, and Industrial Energy Applications, Inc.
(i) OTHER SETTLEMENTS
Other Settlements shall mean the two settlements
filed on April 8, 1994 in Docket No. RS92-45 relating to recovery by
Natural of Supply Realignment Costs from Associated Natural Gas
Company and City of Nebraska City, Nebraska, which settlements were
authorized by the Commission along with the NCG Settlement, and the
settlement filed July 12, 1994 relating to recovery by Natural of
Supply Realignment Costs from Industrial Energy Applications, Inc.,
which settlement was authorized by the Commission in Docket No.
RP94-346 on September 29, 1994, 68 FERC Paragraph 61,388.
(j) G CUSTOMERS
The entities formerly served by Natural under Rate
Schedule G-1 which are listed in Section 38.5(a)(1) of these General
Terms and Conditions and which are covered by the G Customer
Settlement.
(k) G CUSTOMER SETTLEMENT
The settlement filed on August 11, 1994 relating to
recovery by Natural of Supply Realignment Costs from G Customers and
other matters, which settlement was authorized by the Commission in
Docket No. RP94-346 on September 29, 1994, 68 FERC Paragraph 61,388.
(l) INITIAL EFFECTIVE DATE
Initial Effective Date shall mean December 1, 1993.
38.3 APPLICATION OF CHARGES
(a) The charges calculated under Section 38.4 hereof
shall be assessed to members of the Natural Customer Group and Other
Consenting Customers as separate monthly billings of Demand
Surcharges based on fixed transportation billing determinants.