Natural Gas Pipeline Company Of America

Seventh Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 04/18/2008, Docket: RP08-319-000, Status: Effective

Original Sheet No. 360 Original Sheet No. 360 : Pending

 

GENERAL TERMS AND CONDITIONS

----------------------------

 

Natural under transportation Agreement(s). Shippers nominating

volumes to or from pooling points in the Texok Receipt Zone shall

specify the Texok A/G or Texok Gulf Coast Pooling Point, as

appropriate, based upon the Receipt Point(s) of the gas delivered to

the pooling point. Shippers nominating volumes to or from pooling

points in the Iowa-Illinois Receipt Zone shall specify the Amarillo

or Gulf Coast Pooling Point, as appropriate, based upon the Receipt

Point(s) of the gas delivered to the pooling point.

 

9.3 STORAGE POINTS

 

Storage points are imaginary or paper points. There will be

one (1) paper storage point in each receipt zone except that two paper

(2) storage points will exist in the Iowa-Illinois Receipt Zone to

correspond to the two (2) pooling points ("Amarillo Storage Point" and

"Gulf Coast Storage Point"). Shippers will be able to nominate gas

volumes for delivery to or receipt from a storage point as long as such

gas volumes are nominated for simultaneous injection, or withdrawal, as

applicable, under a DSS or storage Agreement(s) with Natural. Volumes

may only be injected or withdrawn under a DSS Agreement at the Iowa-

Illinois storage points. Sourcing of supplies for injection into and

withdrawal from storage points shall be governed by Section 5.6(c) of

these General Terms and Conditions. Storage injections and withdrawals

under Rate Schedule DSS and storage withdrawals under Rate Schedule

FRSS may be on a no-notice basis as provided in those Rate Schedules.

Volumes injected at a storage point under an NSS, PALS or BESS

Agreement may only be withdrawn from that same storage point. Except as

otherwise agreed, volumes withdrawn under an FRSS Agreement must be

injected at the same storage point. Except for Rate Schedule FRSS,

volumes may only be withdrawn or nominated for withdrawal from a

storage point if such volumes were previously accounted for as being

injected at that storage point. Withdrawals under Rate Schedule DSS

shall be governed by the rules set out in Section 5.6. Nominations at a

paper storage point may not be evaluated or rejected based on whether

storage is physically located in the zone. Instead, such nominations

together with no-notice activity shall be evaluated based on Natural's

overall systemwide ability to accommodate volumes tendered for

injection or requested for withdrawal in the zone. If Natural's

capability to accommodate gas tendered for injection into or

withdrawals from any storage point is less than the requested volume,

available storage capability for such storage point shall be allocated

as set out in Section 5 of these General Terms and Conditions.