Natural Gas Pipeline Company Of America
Seventh Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/18/2008, Docket: RP08-319-000, Status: Effective
Original Sheet No. 360 Original Sheet No. 360 : Pending
GENERAL TERMS AND CONDITIONS
----------------------------
Natural under transportation Agreement(s). Shippers nominating
volumes to or from pooling points in the Texok Receipt Zone shall
specify the Texok A/G or Texok Gulf Coast Pooling Point, as
appropriate, based upon the Receipt Point(s) of the gas delivered to
the pooling point. Shippers nominating volumes to or from pooling
points in the Iowa-Illinois Receipt Zone shall specify the Amarillo
or Gulf Coast Pooling Point, as appropriate, based upon the Receipt
Point(s) of the gas delivered to the pooling point.
9.3 STORAGE POINTS
Storage points are imaginary or paper points. There will be
one (1) paper storage point in each receipt zone except that two paper
(2) storage points will exist in the Iowa-Illinois Receipt Zone to
correspond to the two (2) pooling points ("Amarillo Storage Point" and
"Gulf Coast Storage Point"). Shippers will be able to nominate gas
volumes for delivery to or receipt from a storage point as long as such
gas volumes are nominated for simultaneous injection, or withdrawal, as
applicable, under a DSS or storage Agreement(s) with Natural. Volumes
may only be injected or withdrawn under a DSS Agreement at the Iowa-
Illinois storage points. Sourcing of supplies for injection into and
withdrawal from storage points shall be governed by Section 5.6(c) of
these General Terms and Conditions. Storage injections and withdrawals
under Rate Schedule DSS and storage withdrawals under Rate Schedule
FRSS may be on a no-notice basis as provided in those Rate Schedules.
Volumes injected at a storage point under an NSS, PALS or BESS
Agreement may only be withdrawn from that same storage point. Except as
otherwise agreed, volumes withdrawn under an FRSS Agreement must be
injected at the same storage point. Except for Rate Schedule FRSS,
volumes may only be withdrawn or nominated for withdrawal from a
storage point if such volumes were previously accounted for as being
injected at that storage point. Withdrawals under Rate Schedule DSS
shall be governed by the rules set out in Section 5.6. Nominations at a
paper storage point may not be evaluated or rejected based on whether
storage is physically located in the zone. Instead, such nominations
together with no-notice activity shall be evaluated based on Natural's
overall systemwide ability to accommodate volumes tendered for
injection or requested for withdrawal in the zone. If Natural's
capability to accommodate gas tendered for injection into or
withdrawals from any storage point is less than the requested volume,
available storage capability for such storage point shall be allocated
as set out in Section 5 of these General Terms and Conditions.