Natural Gas Pipeline Company Of America

Seventh Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 04/18/2008, Docket: RP08-319-000, Status: Effective

Original Sheet No. 345 Original Sheet No. 345 : Pending

 

 

GENERAL TERMS AND CONDITIONS

----------------------------

 

(i) With respect to the timely nomination/

confirmation process at a receipt or delivery point, in the

absence of agreement to the contrary, the lesser of the

confirmation quantities will be the confirmed quantity. If

there is no response to a Request For Confirmation or an

unsolicited Confirmation Response, the lesser of the

confirmation quantity or the previously scheduled quantity will

be the new confirmed quantity.

 

(ii) With respect to the processing of requests for

increases during the intraday nomination/confirmation process,

in the absence of agreement to the contrary, the lesser of the

confirmation quantities will be the new confirmed quantity. If

there is no response to a Request For Confirmation or an

unsolicited Confirmation Response, the previously scheduled

quantity will be the new confirmed quantity.

 

(iii) With respect to the processing of requests for

decreases during the intraday nomination/confirmation process, in

the absence of agreement to the contrary, the lesser of the

confirmation quantities will be the new confirmed quantity, but in

any event no less than the elapsed-prorated-scheduled quantity.

If there is no response to a Request For Confirmation or an

unsolicited Confirmation Response, the greater of the confirmation

quantity or the elapsed-prorated-scheduled quantity will be the

new confirmed quantity. Elapsed-prorated-scheduled quantity means

that portion of the scheduled quantity that would have

theoretically flowed up to the effective time of the intra-day

nomination being confirmed, based upon a cumulative uniform hourly

quantity for each nomination period affected.

 

(iv) With respect to 8.5 (c) (i), (ii), and (iii), if

there is no response to a request for confirmation or an

unsolicited confirmation response, the Transportation Service

Provider will provide the Service Requester with the following

information to explain why the nomination failed, as applicable:

 

(1) the Service Requester's Transportation

Service Provider did not conduct the confirmation;

 

(2) the Service Requester is told by its

Transportation Service Provider that the upstream confirming party

did not conduct the confirmation;