Natural Gas Pipeline Company Of America
Seventh Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/18/2008, Docket: RP08-319-000, Status: Effective
Original Sheet No. 233 Original Sheet No. 233 : Pending
RATE SCHEDULE LPS
------------------
9.4 In circumstances where Shipper is unable to eliminate
its LPS RO balance because Natural is unable to accept the LPS RO
nomination, Shipper shall take any action to reduce the balance
which Natural can accommodate and Shipper shall be granted
additional time to eliminate its LPS RO balance corresponding to the
time Natural was unable to accept the LPS RO nomination. Shipper
shall not incur any penalty or daily fees as to that portion of the
balance resulting from Natural's inability to accept the LPS RO
nomination. Such extension shall only apply in instances where a
Shipper's inability to eliminate the LPS RO balance is attributable
to Natural's inability to accept and confirm LPS RO nominations.
9.5 Shipper remains responsible to nominate the appropriate
level of transportation to meet Natural's notification requirements
under Section 3 above, or to meet the requirements of the LPS RO.
10. GENERAL TERMS AND CONDITIONS
The provisions of the General Terms and Conditions of this
Tariff, as such provisions may be amended from time to time, are
hereby incorporated by reference and made a part of this Rate
Schedule LPS and shall apply to service rendered hereunder as though
stated herein.